Last updated: November 7, 2024

The entrance on level C02 of the garage will be closed for maintenance on Tuesday, 11/12 from 4 a.m. to 6 a.m.

The Central Plaza Garage (CPG) beneath Red Square is receiving a series of safety improvements from February until autumn. These include upgrading cameras, installing metal gates and card access controls, adding pedestrian doors at vehicle entry/exit points, and improving cell phone coverage on lower levels. While this work is being carried out, access to some parking stalls and garage entrances will be curtailed. Closures will take place in phases to minimize disruption.

This page will always have the latest information about closures, and there will be signs in the garage itself. Affected permit holders for C01-C06 will also be contacted by email.

Schedule

All dates below are estimates and may shift based on circumstances. The most up-to-date information on closures will always be at the top of this page.

  • Feb 14 - July 25: Site fencing & set up laydown area
  • Feb 19 - July 11: Electrical work

  • July 13 - July 1: 15th Ave entry

  • July 5-17:  Stevens Way entry

  • June 11 - July 9: Odegaard entry 

  • July 24 - 30: Grant Lane entry

  • July 30 - August 1: 15th Ave entry

  • August 2-5: Stevens Way entry

  • August 15: Stevens Way entry

  • August 16-19: 15th Ave entry

  • September 25: C01 construction fencing removal

  • September 26: Grant Lane exit reopening

Following the completion of the construction phase above, inspections will begin to take place and be completed towards the end of October. After final inspections, Transportation Services will begin testing and training on the new security systems.