2026
February
Facilities Design Standard - Requirements Common to All Disciplines and Projects
| Section | Item revision/addition | Previous language |
|---|---|---|
| I. Commissioning | I. Commissioning Commissioning plans must include all items to be commissioned, with all systems and equipment requiring verification listed. The Commissioning plan must be submitted to and approved by Engineering Services prior to the first inspection. The commissioning agent shall share the functional performance test scripts with ES prior to execution. ES must receive invitations to witness all performance tests along with respective maintenance shops, with a minimum of 1 week notice. See respective discipline-specific commissioning requirements (i.e. Mechanical, Electrical, Life Safety Alarm Systems, etc.) |
None |
Preferred Manufacturers
| Section | Item revision/addition | Previous language |
|---|---|---|
| Mechanical -> Refrigerant Leak Detection - Early warning alert system | Sensaphone Sentinel Pro SCD-PRO-CD with weatherproof enclosure | None |
| Mechanical -> CCW Valves & Steam Valves | Vanessa by Emerson QUADAX VALVES Inc Tricentric by Trillium |
TYCO, Vanessa Weir, Tricentric QUADAX VALVES Inc. |
| Custodial -> Patient Care Spaces & Approved Variances Only -> Dispenser - Paper Towel | Kimberly Clark 09990 Color back, ABS plastic, professional Sanitouch manual hard roll. Unit size: 12.6” x 16.2” x 10.2”. Paper towel roll core size: 1.5” |
None |
Civil
| Section | Item revision/addition | Previous language |
|---|---|---|
| B. Surveying -> 5. AutoCAD | e. To assist in the coordination of projects during the design development phase, email a courtesy copy of the Topographic Survey (AutoCAD Version) to: UW Facilities - Engineering Services Records records@uw.edu |
e. To assist in the coordination of projects during the design development phase, email a curtesy copy of the Topographic Survey (AutoCAD Version) to: Seethu Babu, PE, CFM UW Facilities - Engineering Services sbabu@uw.edu |
Architectural - Space Data Import Template
| Section | Item revision/addition | Previous language |
|---|---|---|
| Whole document | Added "Space Data Import Template" excel template for room assignments. Document also contains a Flow Chart tab that maps out the process and contact info for groups involved |
Structural
| Section | Item revision/addition | Previous language |
|---|---|---|
| E. Structural Materials -> Concrete | 5. Concrete Chart Provide chart on the structural drawings that clearly indicates each type of concrete used on the project. Include the following minimum information: strength, test age, exposure class, and where each type of concrete is to be used. | 5. Concrete Chart Provide chart on the structural drawings that clearly indicates each type of concrete used on the project. Include the following minimum information: strength, minimum cement content, maximum Water/Cement (W/C) ratio, air-entraining requirements and where each type of concrete is to be used. |
Mechanical - Closed Loop - Pre-Operational Cleaning Checklist
| Section | Item revision/addition | Previous language |
|---|---|---|
| Whole document | Added new instructional checklist document for closed loop water treatment |
Mechanical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design Critera -> Design Criteria | 19. Provide a minimum 3-year extended warranty (instead of standard 1 year) on any products that have been operational in the US market for under 5 years. | None |
| A. Design Critera -> Design Criteria | 20. Do not install piping and ductwork in electrical vaults, rooms or closets except where required for operation of the electrical equipment. Piping and ductwork must never be installed directly over any transformer or switchgear. Drain piping from the floors above shall not be piped through the electrical rooms below. Do not use drip pans as a mitigating means that would allow for the piping to be installed in these areas. a. Sprinklers in secondary electrical rooms installed to protect the electrical equipment are the only exception. Do not install sprinklers in main electrical rooms housing any equipment rated over 600V. Discuss with Engineering Services and EH&S. |
None |
| A. Design Critera -> Inter-discipline Coordination | 6. Coordinate with Architect to ensure there are access doors through walls and hard lid ceilings wherever necessary to reach mechanical equipment. Provide a minimum 24” x 24” size access door. | None |
| C. Air Handlers and Ventilation Fans -> Design Criteria | 1. Provide filtered and conditioned (cooled and heated) mechanical ventilation supply to all occupied building spaces on the UW campus, including but not limited to office, classroom, library, dining, patient care, laboratory, or housing occupancies and elsewhere where required by code or programmatic needs. | 1. Provide filtered and conditioned mechanical ventilation supply to all occupied building spaces on the UW campus, including but not limited to office, classroom, library, dining, patient care, laboratory, and elsewhere where required by code or programmatic needs. |
| E. Hydronic Systems -> Building Chilled Water Systems -> Chilled Water Design Criteria | 12. Cooling towers shall have stainless steel basins. | None |
| E. Hydronic Systems -> Installation, Fabrication, and Construction for All Hydronic Systems | 9. For systems that include an air/dirt separator: a. Critical systems that must remain on at all times must have a bypass on equipment such as heat exchangers, air separators, and meters, b. See Preferred Manufacturer List for preferred vendor. |
9. For systems that include an air/dirt separator, provide a removable head for maintenance, and isolation valves at both the inlet and outlet. a. Critical systems that must remain on at all times must have a bypass on equipment such as heat exchangers, air separators, and meters, b. See Preferred Manufacturer List for preferred vendor. |
| H. Refrigeration -> Design Criteria | 14. Early leak detection: When installing indoor refrigeration equipment with more than 50 pounds of a refrigerant, the project shall include an early leak detection system as described below: a. Ethernet connection to the UW FacNet (secure facility network). b. Panel shall be configured to notify UW Emergency Maintenance (FOMS) at (206) 685-1411 when the level exceeds 100 PPM. c. Note: Early leak detection is separate from the refrigerant detection system required by the fire and mechanical codes for life safety purposes. d. See Preferred Manufacturer List for equipment model. |
None |
| H. Refrigeration -> Products, Materials and Equipment | 1. Provide a minimum 3-year extended warranty option for all refrigeration equipment (parts and labor). | 1. Provide a minimum 3-year extended warranty beyond standard project warranty for compressors (parts and labor). |
| I. Ductwork and Duct Pressure Testing -> Fan-Powered Zone Air Terminal Boxes | 2. Select terminal units with at least 20% extra capacity above design condition. Inlet velocity shall be below 2000 FPM. | None |
| I. Ductwork and Duct Pressure Testing -> Fan-Powered Zone Air Terminal Boxes | 8. Fan powered box sheet metal shall be 20 gauge minimum. Single duct terminal units shall be 22 gauge minimum. | None |
| I. Ductwork and Duct Pressure Testing -> Fan-Powered Zone Air Terminal Boxes | 9. Fan powered boxes shall have 2 inch thick minimum disposable filters. Select minimum MERV 8 with a maximum initial pressure drop of 0.2 inches. | None |
| I. Ductwork and Duct Pressure Testing -> Fan-Powered Zone Air Terminal Boxes | 10. Must provide a control enclosure for terminal unit controls. | None |
| I. Ductwork and Duct Pressure Testing -> Smoke/Fire Dampers | 6. Fire/smoke damper actuators shall be 120V | None |
| I. Ductwork and Duct Pressure Testing -> Access Doors and Panels | 1. Coordinate with Architect to ensure there are access doors through walls and hard ceilings wherever necessary to reach access doors in the HVAC equipment. Provide a minimum 24” x 24” ceiling access door. | 1. Coordinate with Architect to ensure there are access doors through walls and hard ceilings wherever necessary to reach access doors in the HVAC equipment. |
| K. Potable and Nonpotable Water -> Design Criteria | 9. Provide a variable speed hot water circulation pump for both domestic and lab hot water applications. | None |
| K. Potable and Nonpotable Water -> Design Criteria | 30. Provide frost-free, locking hose bibbs every 120 feet minimum along the exterior of the building at grade on each side of the building. Locations shall be verified with UW Facilities Outside Zone (Shop 10). Provide frost-free hose bibbs and/or roof hydrants to allow for cleaning each piece of mechanical equipment, one per roof amenity area, and one for green roof area. Locate to avoid a hose crossing an ADA entrance or by providing on each side of the entrance, locate on each side of obstructing grade separation or features. a. Frost-free hydrants are still required on historical buildings. University will work with landmark groups and the UW design review board to ensure the type, color, style, and locations of frost-free hydrants are suitable. |
30. Provide frost-free, locking hose bibbs approximately every 100 feet along the exterior of the building at grade. Locations shall be verified with UW Facilities Outside Zone (Shop 10). Provide frost-free hose bibbs and/or roof hydrants to allow for cleaning each piece of mechanical equipment, one per roof amenity area, and one for green roof area. |
| K. Potable and Nonpotable Water -> Design Criteria | 33. Dedicated pre-installation meetings are required prior to installing the irrigation point of connection assembly, controller, and pipe and low voltage pathways and envelope penetrations and seals. Assembly must be approved by ES and Outside Zone. | None |
| K. Potable and Nonpotable Water -> Design Criteria -> Water Header Configurations for Lab and Non-Lab Buildings | Revised building water header detail - primarily to add components to irrigation connection | N/A |
| P. Environmental Control Systems -> Sequence of Operations | 2. Operation of multiple supply terminal boxes in a single zone presents special problems. Use a common thermostat or a parent-child control arrangement to avoid conflict between terminal units. Discuss with Engineering Services. | None |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Packaged Controls | 2. Indicate the relationship between the DDC sequence and the dedicated (built-in)packaged controller’s controls sequence for HVAC equipment such as chillers, heat pumps, furnaces, and boilers. DDC sequence shall conform to equipment operating limits and warranty requirements. Review with Engineering Services which parameters to be monitored by the DDC system. | 2. Indicate the relationship between the environmental control system and the dedicated (built-in) controls for specific HVAC equipment such as chillers, heat pumps, furnaces, and boilers. |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Packaged Controls | 3. The enable/disable command and temperature setpoint output from the DDC to the packaged equipment shall be hard-wired. | None |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Packaged Controls | 4. Provide a BACnet interface to monitor packaged mechanical equipment. Provide a key in the DDC graphics that explains the operating codes and alarm codes for packaged equipment. | None |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Packaged Controls | Removed | 4. The building’s environmental control system may offer monitoring and enable the local controls for “on/off.” Review with Engineering Services which parameters to be monitored by the environmental control system. |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Packaged Controls | 7. Third party equipment that integrates with DDC shall be BACnet Testing Laboratory (BTL) certified. | None |
| P. Environmental Control Systems -> Interfacing with DDC with Equipment Built-In Controls | 5. Operation of multiple supply terminal boxes in a single zone presents special problems. Use a common thermostat or a parent-child control arrangement to avoid fighting between terminal units. Discuss with Engineering Services. | 5. Operation of multiple supply terminal boxes in a single zone presents special problems. Discuss with Engineering Services. |
| P. Environmental Control Systems -> Interfacing the DDC with Fire Alarm | 2. The fire alarm system must control life safety mechanical equipment such as those serving shaft pressurization systems, refrigerant machinery rooms, or smoke control systems. Where fans are shut down by the fire alarm system, shut down authority to be effective for all positions of the local hand-off-auto or VFD controls. The DDC system does not control fans after shutdown by the fire alarm system until after reset of the fire alarm system and reset of fire/smoke dampers. Exhaust fans (toilet, fume hood and other non-recirculating) to remain operating, but may require operation at a reduced speed to mitigate pressurization issues. Consult with EH&S for further information. | 2. The fire alarm system must control life safety mechanical equipment such as those serving shaft pressurization systems, refrigerant machinery rooms, or smoke control systems. Where fans are shut down by the fire alarm system, shut down authority to be effective for all positions of the local hand-off-auto or VFD controls. The environmental control system does not control fans after shutdown by the fire alarm system until after reset of the fire alarm system and reset of fire/smoke dampers. Toilet and other non-recirculating exhaust fans to remain on unless this creates a problem of excessive pressure on exit doors. Fume hood fans to remain operating. Consult with EH&S for further information. |
| P. Environmental Control Systems -> Standby Power | 2. Provide a UPS (Un-interruptible Power Supply) having 5 year battery life and battery hot swappable capability for all cabinets containing controllers. Switches and controllers using standby power also need a UPS. | 2. Provide a UPS (Un-interruptible Power Supply) having 5 year battery life and battery hot swappable capability for all cabinets containing controllers. |
| U. Piping, Valves, Pressure Testing, and Accessories -> Products, Material and Equipment -> Piping, Valves, Pressure Testing, and Accessories Table -> Irrigation (Inside) -> Above Grade | Copper type L piping shall be transitioned to type K before any wall penetration that leads to the building exterior. | None |
| X. Water Treatment and Flushing -> Design Criteria | 5. Submit a flushing and water treatment plan for each system prior to pressure testing. Include data sheets for equipment to be provided and parameters set for the procedure; such as media used for flushing, pressure, velocity, temperature, and duration. | 5. Submit a flushing and water treatment plan for each system. Include data sheets for equipment to be provided and parameters set for the procedure; such as media used for flushing, pressure, velocity, temperature, and duration. |
| X. Water Treatment and Flushing -> Design Criteria | 7. Provide inhibited propylene glycol for systems subject to freezing. Glycol concentration shall be a minimum of 25%. Submit a report of the manufacturer and specific chemical contents of all additives, the amounts added, the total volume of the system, and the rated freezing temperature for the specified concentration. | 7. Provide inhibited propylene glycol for systems subject to freezing. Submit a report of the manufacturer and specific chemical contents of all additives, the amounts added, the total volume of the system, and the rated freezing temperature for the specified concentration. |
| X. Water Treatment and Flushing -> Installation, Fabrication and Construction -> General | 5. Submitted water treatment plan shall be approved by the term consultant (currently Homeyer as of 2023). Projects shall complete Closed Loop – Pre-Operational Cleaning document provided by vendor and shall be submitted prior to scheduling service and included in close out documents. | 4. Where new Central Cooling Water is provided, chemically treat according to UW water treatement requirements provided by Engineering Services and CEUO. |
| X. Water Treatment and Flushing -> Installation, Fabrication and Construction -> Flushing/Cleaning and Treatment Methods | 2. Hydrostatic or water flush: Use clean, fresh city water. Do not use water flushing on gas piping. | 2. Hydrostatic or water flush: Use clean, fresh city water. On gas piping, remove water from the entire system after flushing and use the following pneumatic cleaning method to dry the system. |
| X. Water Treatment and Flushing -> Installation, Fabrication and Construction -> Flushing/Cleaning and Treatment Methods | 5. For CCW, perform the system pressure test and flushing in the presence of Engineering Services and CEUO. CCW cannot be used for flushing. Provide temporary pumps, to flush the system with water at a velocity of 5 to 6 feet per second. Provide treated water in accordance with a water treatment plan with approval by CEUO. Schedule with CEUO personnel to request opening the valves to the main CCW system after approval by Engineering Services. Submit all pressure testing and treatment logs to CEUO prior to requesting or scheduling service. | 5. For CCW, perform the system pressure test and flushing in the presence of Engineering Services. CCW cannot be used for flushing. Provide temporary pumps, to flush the system with water at a velocity of 5 to 6 feet per second. Piping to be filled with clean water after flush and prior to opening valves. Notify Power Plant personnel to open the valves to the main CCW system after approval by Engineering Services. |
| X. Water Treatment and Flushing -> Installation, Fabrication and Construction -> Flushing/Cleaning and Treatment Methods | 7. Notify Engineering Services if aluminum components will be introduced to a hydronic system as it can affect water treatment methods. | None |
Electrical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design Critera -> Design Criteria | 12. Spare conduits coming out from building main electrical room shall be 2” and connect to an exterior 12”x12” steel/fiberglass handhole on each side of the building. Conduits shall be sealed to prevent water intrusion. | None |
| A. Design Critera -> Design Criteria | 13. Do not install conduits over transformers and major switchboards not served by said conduits. | |
| U. Lighting -> Basis of Design -> Design Criteria - Exterior Lighting | 1. Do not use uplights, rail lights or bollards for stairway and landscape lighting. | 1. Do not use uplights or bollards for landscape lighting unless approved by Engineering Services and the UW Landscape Committee. |
| U. Lighting -> Basis of Design -> Design Criteria - Exterior Lighting | 2. Do not design lighting into recessed concrete. | None |
| U. Lighting -> Basis of Design -> Minimum Maintained Foot-candle | Minimum Maintained Foot-candle: • 2 Open parking • 1.5 Roadway • 2 Walkways |
Minimum Maintained Foot-candle: • 1 Open parking • 1 Roadway • 0.5 Walkways |
| U. Lighting -> Basis of Design -> Submittals | 3. Submit point-to-point calculations for interior and exterior lighting with point-to-point map and electrical close-out documents. Point-to-point calculations and map must be submitted for review by Engineering Services and the UW Police Department. | 3. Submit point-to-point calculations with electrical close-out documents. |
| V. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 8. Lighting control software or application provided by a vendor shall run on a UW-IT Windows Managed Server provided by the UW. During the design phase, prior to finalizing the specification of the Interior Lighting Control System, the vendor shall provide a test bench to confirm operation and software compatibility with the UW-IT Windows Managed Server. | 8. Lighting control software or application shall be stored on a central server provided by the UW. |
| V. Lighting Control -> Basis of Design -> Design Criteria - Exterior Lighting Control | Removed | 3. Homeruns shall be 1.5" conduit, minimum. |
CAD and BIM Standards - Abbreviated Checklist
| Section | Item revision/addition | Previous language |
|---|---|---|
| 4E | Layering Drawings shall follow the AIA layer standards. Architectural drawings to follow the UW Architectural CAD Standard Layers. Furniture/equipment layers are populated (if applicable). |
Drawings shall follow the Army Corps of Engineers layering standard. Architectural drawings to follow the UW Architectural Standard Layers. |
CAD and BIM Standards - UW Architectural CAD Standard Layers
| Section | Item revision/addition | Previous language |
|---|---|---|
| UW Architectural CAD Standard Layers | Added "Layer Visibility" column, added layer descriptions |
CAD and BIM Standards
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Standards, PDF Requirements, and Compliance Review Submittals -> CAD and BIM Compliance Submittal Review | 11. All AutoCAD and BIM/Revit files shall be georeferenced to real-world coordinates using State Plane Washington North (NAD 1983, State Plane Feet). This is necessary to ensure design deliverables can be directly integrated into UW Facilities’ enterprise GIS, including Space Viewer. | None |
| A. Standards, PDF Requirements, and Compliance Review Submittals -> CAD Standards: | 3. Layering Format c. For architectural layering minimum requirements please see UW Architectural CAD Standard Layers i. Layers “0” and “Defpoints” are permitted but must not contain content. ii. Include designated furniture and equipment layers when applicable to project scope. |
3. Layering Format c. For architectural layering minimum requirements please see UW Architectural CAD Standard Layers i. Layers “0” and “Defpoints” are permitted but must not contain content. |
| A. Standards, PDF Requirements, and Compliance Review Submittals -> CAD Standards: | 4. Scale and Units a. All objects are to be drawn at full scale for the assigned unit of measure. b. All drawings are to have a unit of measure assigned and not set to “unitless”. c. GIS georeferencing standards: i. Coordinate system: State Plane Washington North, NAD 83 HARN. ii. Units: US Feet. iii. Origin (0,0): Defined by survey data (X-Base) or approved GIS/Aerial imagery for placement b.iv. File Setup: Design in Model Space, 1 drawing unit = 1 ft. |
4. Scale and Units a. All objects are to be drawn at full scale for the assigned unit of measure. b. All drawings are to have a unit of measure assigned and not set to “unitless”. |
| A. Standards, PDF Requirements, and Compliance Review Submittals -> BIM Standards: | 5. All Revit files shall be georeferenced to real-world coordinates using StatePlane Washington North (NAD 1983, State Plane Feet) 6. All CAD drawings shall be exported from Revit, maintaining georeferencing to StatePlane Washington North. |
5. All CAD drawings shall be exported from Revit. |
Custodial, Mailing & Waste
| Section | Item revision/addition | Previous language |
|---|---|---|
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 8. Do not implement casework for waste containers. Waste containers are separate and free-standing; they do not go inside shelves, drawers or cabinets. Consult with UW Recycling for waste infrastructure requirements and recommendations. | None |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 9. Do not incorporate grommets / trash drops in casework. | None |
| E. Restrooms -> Design Criteria | 3. Paper towel dispensers can only be put in restrooms within patient care areas. Reference the Preferred Manufacturer List for preferred rolled paper towel dispenser product. Do not incorporate C-Fold or tri-fold paper towel dispensers. | None |
| E. Restrooms -> Design Criteria | 4. In the case of a patient care area restroom or an approved variance, provide one wall-mounted paper towel dispenser per every 2 sinks in restrooms. Contact the custodial department for variance approval. | None |
Exterior Improvements - Irrigation
| Section | Item revision/addition | Previous language |
|---|---|---|
| Basis of Design | A significant overhaul of the Irrigation Design Standards expands on previous standards, and now generally includes the following changes/additions:
|
N/A |
Exterior Improvements - Trees design and construction
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added new document "Orange Sheet - Tree Planting & Protection" | ||
| Added new document "Green Sheet - Tree Protection" |
Plants and Trees Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 2 - PRODUCTS -> 2.01 MATERIALS | Added 3 details: Root Correction Detail – Balled and Burlapped Crown Correction Detail Root Ball Shaving Container Detail |
None |
Trees - Additional Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 0 - PRE CONSTRUCTION AND SITE PLANNING | 1. Site Planning: See Orange Sheet – Tree Planting & Protection for highlighted Design Considerations | None |
| PART 0 - PRE CONSTRUCTION AND SITE PLANNING | 3. An evaluation of the existing trees on a site is required prior to design. This evaluation will be conducted by a third-party Arborist for projects costing greater than 10 million. a. Request a Shapefile of the most current tree data within 50 feet of the project scope from the Campus Arborist. b. Use the UW campus tree numbers and verify all inventory information. c. If trees in the field are not listed, identify the tree with a “Letter” identifier. d. Send data in GIS Shapefile format to the UW Campus arborist. |
3. An evaluation of the existing trees on a site is required prior to design. This evaluation will be conducted by a third-party Arborist for projects costing greater than 10 million. Send data in spreadsheet (excel) format to the UW Campus arborists |
| PART 0 - PRE CONSTRUCTION AND SITE PLANNING | 3. Mitigation payments in lieu of planting is calculated and billed at substantial completion of the project. b. Large (at maturity) trees may reduce mitigation at a higher rate. Contact the UW arborist for more details. |
3. Mitigation payments in lieu of planting is calculated and billed at substantial completion of the project. |
| PART 1 - GENERAL -> 1.04 PRECONSTRUCTION CONFERENCE | 5. Download and distribute the “Green Sheet – Tree Protection” document to contractors and subcontractors. | None |
| PART 2 - PRODUCTS -> 2.01 TREE PROTECTION | A. Signage: 1. The Construction Manager will provide a Work Order number to the University of Washington Campus Arborist to create and attach tree protections signs and Green Sheets at predetermined locations or 20 foot intervals. i. Tree Protection signs details: 24 inches wide X 18 inches tall on corrugated cardboard with grommets. Shall be posted on tree protection fencing at predetermined locations or 20 feet intervals. Sign will include the name and phone number of the UW Construction Manager and the sum assessed value of trees within the project site. ii. Green Sheet sign details: 8.5 inches x 11 inch laminated corrugated cardboard signs with grommets |
A. Signage: 1. The University of Washington Construction Manager will provide Tree Protection signs 24 ches wide X 18 inches tall to be posted on tree protection fencing at predetermined locations or 20 feet intervals. |
| PART 2 - PRODUCTS -> 2.01 TREE PROTECTION | 2. Signs: Attach 8.5 inches x 11 inch laminated "Green Sheet" signs to the tree protection fence at 20-foot intervals or locations predetermined by the project/campus arborist. | 2. Signs: 8.5 inches x 11 inches, the signs shall be attached to the tree protection fence at 20-foot intervals. |
| PART 3 - EXECUTION -> 3.02 TREE AND PLANT PROTECTION AREA -> F. Protection of existing trees and shrubs: | 2. Trees indicated to remain within the Project Site shall have protection fencing or tree trunk boxing that shall be maintained by the Contractor in good condition until Substantial Completion. i. If the project landscaping phase requires fence alteration or removal, contact the project arborist or campus arborist for a consultation on temporary tree protection. ii. Tree protection fencing must be installed unless work is currently in progress. |
2. Trees indicated to remain within the Project Site shall have protection fencing or tree trunk boxing that shall be maintained by the Contractor in good condition until Substantial Completion. |
EH&S - Emergency Washing Equipment
| Section | Item revision/addition | Previous language |
|---|---|---|
| 1. Applications | When emergency showers are located in a corridor, other public spaces, or near sensitive equipment, provide showers with stalls equipped with a sloped floor or shower pan, plumbed floor drain, and privacy curtain. This is to encourage shower use and prevent flooding, as it can mitigate the damage from malicious activation of the showers in corridors or other public areas. Verify all floor drain requirements with EH&S. | To encourage shower use and prevent flooding, provide showers with stalls equipped with a sloped floor or shower pan, plumbed floor drain, and privacy curtain. This can also mitigate the damage from malicious activation of the showers in corridors or other public areas. |
EH&S - Life Safety Alarm Systems
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added new design standard document for gas detection and alarm systems | N/A |
EH&S - Environmental Protection Requirements
| Section | Item revision/addition | Previous language |
|---|---|---|
| 2. Stormwater Management | For the City of Bothell, Bothell’s Surface Water Design Manual outlines drainage review. It is at: https://www.bothellwa.gov/353/Bothell-Standards | For the City of Bothell, Bothell’s Surface Water Design Manual outlines drainage review. It is at: http://www.ci.bothell.wa.us/1239/Design-Manual |
August
Facilities Design Standard - Requirements Common to All Disciplines and Projects
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Safe Access -> Roof and Building Envelope | All new buildings, major renovations, and roof replacements shall provide a new or updated Safe Access Plan for both roof and envelope safe access. The Safe Access Plan shall be submitted to the UW Facilities Safety Department and Engineering Services for review no later than 30% Design submittal. All new building fall safety systems shall implement "passive fall protection" (i.e. parapets, railings, guardrails, etc) of 42" minimum and shall provide at least 12ft wide unobstructed access for a 35,000lb lift at minimum at the building exterior perimeter for envelope access. Any deviation from this standard (i.e. life lines, roof anchors, and/or davit systems) shall be submitted as part of a FDS Variance Request. Roof anchors may be required in addition to "passive fall protection" to provide over-the-side envelope access. All proposed roof anchors, davits, lifts, etc shall be included in the Safe Access Plan. Major renovations and roof replacements may require a combination of the systems noted above to provide roof and envelope safe access. All fall arrest and safe access design shall adhere to the Fall Protection Program Manual PDF on the EH&S Fall Protection webpage. | Fall safety systems for new buildings, major renovations, and roof replacement projects shall implement "passive fall protection" (i.e. parapets, railings, guardrails) of 42" or higher. Any deviation from this standard (i.e. life lines and roof anchors) shall be vetted and will need approval from UW Facilities senior leadership. In some cases, even with “passive fall protection” systems, roof anchors for over-the-side work may still be needed for window washers, glaziers, and building envelope repair and maintenance. Roof anchors may be avoided if there is unobstructed access for a lift all around the perimeter of the building. Lifts should be able to reach the top of exterior walls. All proposals for roof anchors or lift access around the perimeter of the building shall be vetted and approved by a representative from UW facilities senior leadership. |
| A. Safe Access -> Roof and Building Envelope | Coordinate building envelope maintenance equipment with UW Facilities Equipment Operations Shop: including but not limited to swing stage anchors/loads and fall arrest anchors, etc. at pre-design or like phase to accommodate equipment that is often used to drive around the building to perform maintenance. | None |
| A. Safe Access -> Maintenance Access Plan for Hazardous Spaces | Some examples of proper safe access design: Locate equipment and accessories above and in ceilings such that ladder placement avoids interference from casework, lab benches, sinks, adjacent walls, or lab equipment. Give consideration to ceiling tiles immovable due to sprinkler heads, light fixtures, or other ceiling mounted devices. |
None |
| C. Coordination | 7. Structural, Mechanical, and Electrical: Vibration, noise, & exhaust – Careful consideration must be taken when determining the location of equipment that produces noise, vibrations and exhaust. Products or processes that create hazardous fumes, or excessive or offensive noise may be restricted. | None |
| E. Preferred Manufacturers | Spare parts inventories, prior experiences of the University, and staff training on the operation and maintenance of sophisticated equipment may restrict the list of suppliers to three or less, even though more suppliers with similar equipment may exist. Typical industry standard equipment may not always be appropriate for use on University projects. | None |
| E. Preferred Manufacturers | Any components or parts with lead times exceeding 8 weeks and/or requiring bulk quantity batch orders shall have additional attic stock provided per the direction of the UWF Maintenance zone manager. | None |
| I. Major Renovations | Include an evaluation for building system renovation projects which describes the condition of the building systems, variances from present codes, and identifies spare system capacity or system deficiencies and opportunities for improving energy efficiency. The design team’s mechanical, electrical, civil, structural, and architectural disciplines participate jointly in this evaluation. The abandonment of existing equipment and material in place is not acceptable. Conserve space as much as possible. |
None |
Variance Request
| Section | Item revision/addition | Previous language |
|---|---|---|
| FDS Variance and LCCA Log (xlsx) | Added the following columns: LCCA SUBMITTED? (Y/N) LIFECYCLE ENERGY SAVINGS (kWh) LIFECYCLE GHG SAVINGS (mTCO2e) LIFECYCLE WATER SAVINGS (CCF) LCCT/eLCCA OUTCOME (Approved/Denied) |
Asset Data Management
| Section | Item revision/addition | Previous language |
|---|---|---|
| Whole documents | Added the following documents: Gathering Asset Data and Loading it into AiM AssetSync Asset Data Added the following instruction: All projects that add or remove assets must follow the process in the below documents and submit a completed AssetSync spreadsheet for asset data and AiM implementation. |
- |
Preferred Manufacturers
| Section | Item revision/addition | Previous language |
|---|---|---|
| EH&S -> Freezers (-80°F) | Sterling Thermodyne Or approved equal |
None |
| Mechanical -> Press Fittings | Viega FNW (for Domestic, Lab, and Low water temp. <140) Nibco (for Domestic, Lab, and Low water temp. <140) No substitutions |
None |
| Electrical -> Lighting Luminaire Internal Disconnects | Thomas & Betts, Cat. No. LD-2, Sta-Kon disconnects Ideal 30-382J, Powerplug Luminaire wire standards version Or Approved Equal |
None |
| Architectural -> Keys | Chicago Olympus Lock National Lock |
Chicago |
| EH&S -> Fume Hoods Low Flow (70 fpm) | Kewaunee Supreme Air LV Labconco Xstream Mott SafeguardTM No Substitutions |
Kewaunee Supreme Air LV Labconco Xstream No Substitutions |
| Custodial -> Wall-Mounted Hand Dryer | Dyson Air-blade HU02 Unit size: 31 ½ x 15 1/3 stainless steel back panel |
None |
| Custodial -> Dispenser - Soap | GOJO FMX-12 1250ml. unit size: 10” x 6” x 5”. SKU: 5150-PL (plain, no logo). color grey. ADA compliant. Alternate: GOJO FMX-20 GPH. 2000ml |
None |
Civil
| Section | Item revision/addition | Previous language |
|---|---|---|
| I. Water Quality / Onsite Stormwater Management (OSM) | 13. If project area drains to a combined sewer system (CSO), storm water shall be separated to a dedicated storm system, and existing CSO shall be replaced with separated dedicated storm and sewer systems. | None |
Architectural
| Section | Item revision/addition | Previous language |
|---|---|---|
| B. Shell -> Shell -> Exterior Vertical Enclosure -> PARAPETS (B2010.50) | 5. Parapets shall be 42" minimum. | 5. Parapets shall be 42" +/- 3” or higher |
| B. Shell -> Shell -> Exterior Vertical Enclosure -> EXTERIOR WINDOWS -> Windows (08 50 00) | 2. Window Louvers and exterior shades – design must take into account washing and maintenance when designing window louvers or exterior shades for solar heat gain. Engineering Services and Building Services must review for safe access. See the Requirements Common to All Disciplines and Projects document for Safe Access Plan requirements. | None |
| C. Interiors -> Construction -> INTERIOR DOORS (C1030) -> Hardware (08 71 00) | 1. Final keying is by UW Facility Services Lock Shop. All alternatives must be approved by the Lock Shop. | 1. Construction keying and final keying is by UW Facility Services. |
| C. Interiors -> Construction -> INTERIOR DOORS (C1030) -> Hardware (08 71 00) | 1. NO narrow style hardware is allowed; Wide styles only. All doors shall accept full size Mortise pockets and full-size Panic devices. | 1. NO narrow style hardware is allowed; medium or wide styles only. |
| C. Interiors -> Construction -> INTERIOR DOORS (C1030) -> Hardware (08 71 00) | 7. All exterior doors must have top and bottom latches with strikes and must be surface mounted. Center latching single point devices are acceptable. No concealed cable rods are permitted on University of Washington buildings. | 7. All exterior doors must have top and bottom latches andwith strikes and must be surface mounted. Center latching single point devices are acceptable. Surface mounted strikes with vertical rods are preferred. No concealed cable rods are permitted on University of Washington buildings. |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.01 PRODUCTS -> B. HINGES | 1. Manufacturer: McKinney, Ives 2. Acceptable Substitutions: None 7. Continuous Hinges: Provide Heavy Duty Continuous Gear Hinges at Aluminum Entries. Accepted Manufactuers - Pemko, Ives |
1. Manufacturer: Bommer 2. Acceptable Substitutions: Hager, Stanley 7. Continuous Hinges: Provide Heavy Duty Continuous Gear Hinges at Aluminum Entries. |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.01 PRODUCTS -> C. LOCKSETS | 1. Manufacturer and Series: Corbin Russwin ML2000 Series, Schlage L9000 Series 2. Acceptable Substitutions: None 3. Lever and Rose Design: NSB, 06B 6. Electrified Locksets: a. Provide 24VDC. Maximum continuous current 330mA. b. Provide Storeroom function unless otherwise directed. c. Locks shall be by OEM, or modification by ACSI. d. Field adjustable for fail-safe and fail-secure. |
1. Manufacturer and Series: Schlage L9000 2. Acceptable Substitutions: Corbin ML2000 (with approval by UW Lock Shop) 3. Lever and Rose Design: 06B |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.01 PRODUCTS -> E. EXIT DEVICES | 1. Manufacturer and Series: Corbin Russwin ED5000 Series, Von Duprin 98 Series. 2. Acceptable Substitutions: None 3. Trim: N955 with NA Lever Design, 996L with 06 Lever Design 7. Removable Mullions: Provide Key Removable Steel Mullions . Accepted Manufactures - Corbin CR972BKM Series, Von Duprin KR4954 or KR9954 Series. Aluminum Mullions are unacceptable. |
1. Manufacturer and Series: Von Duprin 35 and 98 Series. 2. Acceptable Substitutions: Corbin ED4000 and ED5000 3. Trim: 996L with 06 Lever Design 7. Removable Mullions: Provide Key Removable Steel Mullions . Von Duprin KR4954 or KR9954 Series. Aluminum Mullions are unacceptable. |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.01 PRODUCTS -> G. AUTOMATIC OPERATORS AND ACCESSORIES | 1. Manufacturer: Record 2. Acceptable Substitutions: LCN 6400 with UW Building Access Group approval only. 3. Series: a. 8100 for exterior, vestibule, service, and cross corridors. b. 6100 for suite entries. c. LCN 6400 for limited low use applications with Building Access Group approval. 4. Mounting with factory provided fasteners only. 8. Switches: a. Provide Activation Switches with ADA compliant Logo. Allen wrench concealed mounting fasteners. b. Acceptable Manufacturers: Camden, Larco, BEA c. No wireless activations switches are acceptable. |
1. Manufacturer: Record 2. Acceptable Substitutions: None 3. Series: a. 8100 for exterior, vestibule, service, and cross corridors. b. 6100 for suite entries. 8. Switches: a. Provide Activation Switches with ADA compliant Logo. Allen wrench concealed mounting fasteners. b. Acceptable Manufacturers: Camden, Larco, BEA |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.01 PRODUCTS -> | H. KICK, MOP, AND ARMOR PLATES 1. Manufacturer: Rockwood, Trimco 2. Acceptable Substitutions: Ives I. OVERHEAD STOPS 1. Manufacturer: Rixson, Glynn Johnson 2. Acceptable Substitutions: None J. WALL STOPS 1. Manufacturer: Rockwood, Trimco 2. Acceptable Substitutions: Ives K. FLOOR STOPS 1. Manufacturer: Rockwood, Trimco 2. Acceptable Substitutions: Ives L. PIPE STOPS 1. Manufacturer: Rockwood, Trimco 2. Acceptable Substitutions: None 3. Types: 466RKW, 1209HA M. PIPE STOP AND HOLDERS 1. Manufacturer: ABH Manufacturing, Rockwood 2. Acceptable Substitutions: None 3. Types: 1804, 491, 494 N. ELECTRO-MAGNETIC WALL HOLDERS 1. Manufacturer: Rixson, LCN 2. Acceptable Substitutions: None H. THRESHOLDS, WEATHERSTRIP, AND SMOKE GASKET 1. Manufacturer: Pemko, NGP 2. Acceptable Substitutions: Zero |
H. KICK, MOP, AND ARMOR PLATES 1. Manufacturer: Rockwood, Trimco 2. Acceptable Substitutions: Hager, Ives I. OVERHEAD STOPS 1. Manufacturer: Rixson, Glynn Johnson 2. Acceptable Substitutions: ABH J. WALL STOPS 1. Manufacturer: Trimco 2. Acceptable Substitutions: Hager, Ives K. FLOOR STOPS 1. Manufacturer: Trimco 2. Acceptable Substitutions: Hager, Ives L. PIPE STOPS 1. Manufacturer: Trimco 2. Acceptable Substitutions: Rockwood 3.Types: 1209HA M. PIPE STOP AND HOLDERS 1. Manufacturer: ABH Manufacturing 2. Acceptable Substitutions: None 3. Types: 1804 N. ELECTRO-MAGNETIC WALL HOLDERS 1. Manufacturer: ABH 2. Acceptable Substitutions: DynaLock, LCN H. THRESHOLDS, WEATHERSTRIP, AND SMOKE GASKET 1. Manufacturer: Pemko, NGP National Guard 2. Acceptable Substitutions: Reese, Zero |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.02 MISCELLANEOUS HARDWARE REQUIREMENTS | A. Miscellaneous Lock Cylinders: Contact the UW Lock Shop for appropriate specification. E. Provide door closers on all doors at all electrified openings and spaces leading to non-public areas like mechanical and electrical rooms to help ensure that doors are not inadvertently left open. |
A. Miscellaneous Lock Cylinders: Provide Cylinders, keyed to system, for Elevator Controls. Coordinate Cylinder and Cam types with equipment Elevator Manufacturer. E. Provide door closures on all doors leading to non-public spaces like mechanical and electrical rooms to help ensure that doors are not inadvertently left open. |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.03 KEYING | A. All Keyed products specified under this Section shall be determined by the Lock Shop. B. Provide Construction Cylinders and Keys during the construction period. C. All Building keying systems shall be provided by Lock Shop (Owner). F. The General Contractor shall be responsible for: 1. All door hardware templates and deadlines are communicated in a timely manner to the Lock Shop. 2. The installation of all cylinders and security of all Permanent Key System keys checked out during the installation and job close out and punchlist phase of the project. |
A. All Keyed products specified under this Section shall be keyed to the existing Medeco 3 Key System. B. Provide Construction Cylinders and Keys during the construction period. F. The General Contractor shall be responsible for: 1.The installation of all cylinders and security of all Permanent Key System keys checked out during the installation and job close out and punchlist phase of the project. |
| C. Interiors -> Construction -> INTERIOR DOORS STANDARD SPECIFICATIONS (08 71 00) -> 1.04 APPLICATION NOTES | A. Lockset and Exit Device Functions: 1. Classroom Locksets: Double Cylinder locking, Corbin ML2052 or ML2002 V11, Schlage L9071 2. Office Locksets: Corbin ML2054, Schlage L9050 3. Interior Privacy Locksets: Corbin ML2060 V50 VO-WB, Schlage L9040 L283-722 4. Single Occupancy Restrooms: Corbin ML2065 V50, Schlage L9056 5. Faculty Restrooms: Corbin ML2059 V50, Schlage L9485 D. Doors: 1. All Aluminum storefront openings to be approved by Building Access Group/Lock Shop during design. 2. Restrict Doors to commons sizes for ease of replacement and repair. Review use of Doors over 8’-0” height with UW Carpentry Shop. 3. Glass Door Hardware to be approved by Building Access Group/Lock Shop during design. |
A. Lockset and Exit Device Functions: 1. Classroom Locksets: Double Cylinder locking, Schlage L9071 2. Office Locksets: Schlage L9050 3. Interior Privacy Locksets: L9040 with Occupancy Indicator L283-722 4. Corridor Multiple Occupancy Restrooms: Classroom Deadlock L463 D. Doors: 1. Restrict Doors to commons sizes for ease of replacement and repair. Review use of Doors over 8’-0” height with UW Carpentry Shop. 2. Glass Door Hardware to be approved by Building Access Group/Lock Shop during design. |
| C. Interiors -> Finshes -> Flooring Treatment (C2030.10) | 3. For concrete or wood floors and stairs, and also vestibules/building entrances, see requirements in the Custodial, Mailing and Waste document General Building Design – Custodial Servicing section. | None |
Structural
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. General Requirements -> Building Envelope Maintenance Equipment | Refer to Roof and Building Envelope Safe Access requirements in the Requirements Common to All Disciplines and Projects document for roof and envelope access for maintenance and repair. Refer to the UW EH&S Fall Protection Program Manual for additional information and requirements. Structure shall be designed to support the shear loading and overturning moment for all roof anchors and davits. Loading assumptions shall be provided in general notes and structural details. |
Coordinate building envelope maintenance equipment: including but not limited to swing stage anchors/loads and fall arrest anchors, etc. at pre-design or like phase to accommodate equipment that is often used to drive around the building to perform maintenance. The Safe Access plan to maintain the building equipment shall be provided at pre-design or like phase. |
Metering & Monitoring specifications, DDC specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| Whole documents | Added 4 DDC specification documents: DDC Standard Specifications DDC Graphics Specifications DDC Point Name Convention Specifications DDC Alarms and Trends Specifications |
- |
Electrical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design Criteria | Consolidated formerly "General Requirements" section into "Design Criteria" section | - |
| A. Design Criteria -> Design Criteria | 7. Mount main service equipment (included but not limited toe.g. transformers, free standing switchboards, MV switches) on a 4” minimum reinforced concrete pad secured to structural slab. Size concrete pads larger than equipment. Extend the pad at least ten times the diameter of the mounting bolts past the equipment, at least a minimum of 3” past the equipment. Coordinate with Structural Engineer for final design. | 7. Mount main service equipment (included but not limited toe.g. transformers, free standing switchboards) on a concrete pad secured to structural slab. Size concrete pads larger than equipment. Coordinate with Structural Engineer for final design. |
| A. Design Critera -> Design Criteria | 11. Main electrical rooms housing medium voltage normal and emergency power transformers and associated electrical equipment shall be designed to not require fire sprinklers. A formal request(s) to the city must be made per the International Fire Code. Consult with Engineering Services and Environmental Health & Safety Senior Fire Protection Engineer. | None |
| B. Primary Distribution | 3. Service conductor ductbanks shall be concrete encased and provided with an additional 25% spare cells for future services or cable replacements. Consider ductbank conductor derating per NEC when sizing the conductors and raceways. For these purposes, conductors larger than the University standard sizes may be required. For example, where 500kcm feeders need to be routed through a ductbank to reach their destination, they may have to be sized to 750kcm in order to retain the power delivery capacity of the feeder. | 3. Service conductor ductbanks shall be concrete encased and provided with spare cells for future services or cable replacements. Consider ductbank conductor derating per NEC when sizing the conductors and raceways. For these purposes, conductors larger than the University standard sizes may be required. For example, where 500kcm feeders need to be routed through a ductbank to reach their destination, they may have to be sized to 750kcm in order to retain the power delivery capacity of the feeder. |
| U. Lighting -> Basis of Design | 3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star). • Fixtures shall be the type that has a separate driver and LED array assembly can be replaced without having to replace the entire fixture. |
3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star). • Fixtures shall be the type that LED lamp array assembly can be replaced without having to replace the entire fixture. |
| U. Lighting -> Products, Materials and Equipment | 1. Recessed downlights shall have a minimum diameter of 4 inches. 2. Supply luminaire parts with internal disconnects. See Preferred Manufacturer List for internal disconnects. |
1. Mount flat lenses in frames designed for replacement with lenses up to .38 inch thick. a. Use clear plastic lenses that are 0.125 inch minimum thickness virgin acrylic. b. Use pattern 12 lenses where a diffuse light source is desired. c. Pattern 15 lenses are preferred to minimize imaging on video monitors. d. Use sealed luminaires with Corning pattern 79 glass lenses in sterile areas. 2. Supply luminaire parts with internal disconnects. Sta-Kon disconnects by Thomas & Betts, Cat. No. LD-2, or equal are required. |
| V. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | Install a Milbank lockbox per UW-IT specifications that will house the FacNet data outlet for communication on the secure UW Facilities IT network located at a maintainable height and no farther than 10’ away. Only data outlets for communication on the secure Facilities network will be installed in the MilBank lock box, data outlets for communication on the UW campus IT network are to be installed outside of the lock box. | Provide public network port with Facnet port next to Lighting controller Brain |
| Z. Wiring Devices -> Basis of Design -> Design Criteria | 9. Refer to the Custodial, Mailing and Waste standards for electrical outlet requirements in hallways, stairwells, custodial closets, and building parapets. | None |
| Z. Wiring Devices -> Products, Materials and Equipment | 5. Covers for wiring devices and switches shall be nylon. Plastic covers are not allowed. | None |
| Z. Wiring Devices -> Installation, Fabrication and Construction | 2. Install receptacle so the ground terminal is on top. | None |
Mechanical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design Critera -> Inter-discipline Coordination | 5. When installing freezers, especially in lab spaces, account for added cooling and electrical load and seismic bracing required. Refer to EH&S Preferred Manufacturer List for freezer preferred vendors. | None |
| C. Air Handlers and Ventilation Fans -> Design Criteria | 2. Size ventilation system to provide at least 20% additional capacity above minimum system design requirements. | 2. Size air handler to provide at least 20% additional ventilation (outdoor) air volume above system design. |
| C. Air Handlers and Ventilation Fans -> Products, Materials and Equipment -> Fume Hood Exhaust | 12. New or relocated fume hoods must pass the UW fume hood certification process. See the Laboratory Ventilation standards for requirements. | None |
| E. Hydronic Systems -> Design Criteria for All Hydronic Systems | 5. Refer to EH&S Emergency Washing Equipment document for eyewash equipment requirements at locations where chemical transfer occurs. | None |
| E. Hydronic Systems -> Building Chilled Water Systems -> Programming | 4. Cooling towers must be located at a minimum of 50 horizontal feet from all nearby air intakes of any building. Give special consideration to the location of cooling towers concerning noise to the occupants and local residential areas. | 4. Give special consideration to the location of cooling towers with respect to contamination of the building fresh air intake, intakes of nearby buildings and noise to the occupants and local residential areas. |
| F. Building Steam and Condensate | 9. Discuss temporary heating with Engineering Services and Campus Energy Utilities and Operations. | 9. Discuss temporary heating with Engineering Services. Consider natural gas or electric-driven equipment in lieu of steam. If steam is used for temporary heat, dump condensate to sanitary sewer by tempering to below 140 °F. |
| K. Potable and Nonpotable Water -> Design Criteria | 9. Confirm with Engineering Services where and if lab hot water is needed – lab hot water fixtures frequently are not used and can cause leaks from stagnant water. | None |
| K. Potable and Nonpotable Water -> Design Criteria | 22. Refer to the Green Building Standard for fixture flow rates, unless otherwise specified by code. | |
| K. Potable and Nonpotable Water -> Design Criteria | 24. Provide two water fixtures at custodial closets – one faucet at the mop sink level for bucket filling, and one mounted higher for soap feed connection (hose bibb acceptable for upper fixture). Refer to the Custodial, Mailing & Waste standards for plumbing requirements in custodial rooms. | None |
| P. Environmental Control Systems | Refer to the CEUO DDC Specifications in conjunction with this section. | None |
| P. Environmental Control Systems -> Hardware and Software | 4. Actuators – provide low voltage 24V actuators. a. Exception: Provide pneumatic actuators for all steam control valves in existing buildings where pneumatic control is available. |
4. Actuators – provide low voltage 24V actuators. a. Exception: Provide pneumatic actuators for all steam control valves. |
| U. Piping, Valves, Pressure Testing, and Accessories -> Design Criteria | 5. Refer to the Piping, Valves, Pressure Testing, and Accessories Table document for pipe material, joints, fittings, valves, and testing pressure requirements. | None |
| U. Piping, Valves, Pressure Testing, and Accessories -> Design Criteria | Consolidated 10 separate tables into a new Piping, Valves, Pressure Testing, and Accessories Table, streamlining requirements and reflecting significant updates to piping requirements. | Tables P-1 through P-10 |
| U. Piping, Valves, Pressure Testing, and Accessories -> Installation, Fabrication and Construction -> Pipe Fittings | 5. Do not locate press or grooved fittings in shafts or other inaccessible locations. | None |
| U. Piping, Valves, Pressure Testing, and Accessories -> Installation, Fabrication and Construction -> Pipe Fittings | 6. Do not use press or grooved fittings within 10 ft of heat generating equipment (such as heat exchangers, boilers, etc.). | None |
| U. Piping, Valves, Pressure Testing, and Accessories -> Installation, Fabrication and Construction -> Valves | 8. Chain operators – install valves in equipment rooms or fan rooms used for equipment or coil isolation more than 8 feet above floor with stem horizontal and equipped with chain wheels and chains extending to 6 feet above floor. Provide a chain operator where valve is not easily accessible, and see the Maintenance Access Plan for Hazardous Spaces section of the Requirements Common to All Disciplines and Projects document. | None |
Conveyance Standard Specification
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Architectural -> PART 2 - PRODUCTS -> 2.05 ELEVATOR CAR | 8. COMMUNICATION PLATFORM: A Rath Smartview 2 two-way elevator communication platform shall be installed to meet ASME A17.1 2019/CSA B44-19. | None |
Exterior Improvements - Irrigation
| Section | Item revision/addition | Previous language |
|---|---|---|
| Basis of Design | 7. Provide quick coupler valves every 100 feet or less and at all mainline terminations. These quick coupler valves are used to hand water landscaped areas. Locate quick coupler valves to limit water hoses crossing walkways and roads. | 7. Provide quick coupler valves every 100 feet or less. These quick coupler valves are used to hand water landscaped areas. Locate quick coupler valves to limit water hoses crossing walkways and roads. |
| Basis of Design | 8. Provide quick coupler valves as follows: a. Every 100 feet or less of piping b. At all mainline terminations c. In a way as to limit water hoses crossing walkways and roads d. Quick coupler valves are used to hand water landscaped areas. In addition to providing water sources, quick coupler valves are located at mainline terminations to allow the safe discharge of stored compressed air energy when filling empty or partially empty mainlines. |
None |
| Basis of Design | 23. Provide a minimum of two looping spare control and common wires for every (6) control wires on each mainline branch and to maintain terminations enclosed in a Carson 910 valve box, black, tee lid, labelled ‘irrigation’. Additional non-looping spares wires and a common wire may be added during design to stage capacity for future expansion. | 22. Provide a minimum of two spare control wires to all remote mainline legs. Additional spares may be requested during design to offer the potential for expansion |
Plant & Trees Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 3 - EXECUTION -> 3.05 ADJUSTING | A. Tree Pruning: Tree structural pruning should be restricted to injured, broken, dead or crossing branches. Prune in accordance with standard horticultural practice established by the International Society of Arboriculture. 1. Unless otherwise directed by Architect, do not cut tree leaders, and remove only injured, broken or dead branches from trees. |
A. Tree Pruning: Prune, thin out, and shape trees and shrubs in accordance with standard horticultural practice established by the International Society or Arborists. Do no pruning prior to approval by Architect. 1. Prune trees to retain required height and spread, and at no time more than 1/5 of the plant. 2. Unless otherwise directed by Architect, do not cut tree leaders, and remove only injured, broken or dead branches from trees. |
| PART 3 - EXECUTION -> 3.07 LANDSCAPE MAINTENANCE | 8. Tree Management: b. Pruning: All tree pruning must be conducted by the project field arborist unless otherwise directed by the University of Washington Grounds Representative. |
No previous language for item 8-b |
Trees - Additional Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 1 - GENERAL -> 1.02 SUBMITTALS | C. Arborist Report: Prior to the start of construction, submit, for approval by the Owner’s Representative, the report of a consulting arborist who is a registered Consulting Arborist® (RCA) with American Society of Consulting Arborists, or an ISA Board Certified Master Arborist, which details the following information for all trees to remain within the area designated on the drawings as the Tree and Plant Protection Area. Prior to conducting the site visit, obtain a preliminary template from the University of Washington indicating the tree numbers, species, and approximate measurements. Use the UW tree numbers in the Arborist Report. Trees missing numbers should be given a “Letter“ description and cross referenced with the University of Washington inventory to either replace the original number or create a new number. The arborist report shall include the following: 2. A description of each tree outside the project scope that may be impacted by equipment travel routes, pedestrian desire routes or equipment and supply storage 6. Indicate the Tree Protection Area (radius in feet) for each tree. |
No previous language for item C numbers 2 and 6 |
| PART 2 - PRODUCTS -> 2.01 TREE PROTECTION | A. Signage: 1. The University of Washington Construction Manager will provide Tree Protection signs 24 inches wide X 18 inches tall to be posted on tree protection fencing at predetermined locations or 20 feet intervals. |
A. Signage: 1. The Contractor shall post weather resistant 8 1/2" x 11” signs using the UW Protect Tree Template. |
| PART 2 - PRODUCTS -> 2.01 TREE PROTECTION | B. Fencing: 1. Protection fencing shall be equal to the following: b. PLASTIC MESH FENCE: Under certain circumstances, the project arborist or UW Campus Arborist may approve heavy-duty orange plastic mesh fencing fabric 48 inches wide. This fencing must be approved in writing and shared with the Campus Arborist, Consulting Arborist and UW Project Manager. Fencing shall be attached to metal “U” or “T” post driven into the ground of sufficient depth to hold the fabric solidly in place without sagging. The fabric shall be attached to the post using attachment ties of sufficient number and strength to hold up the fabric without sagging. The Owner’s Representative may request, at any time, additional posts, deeper post depths, and/or additional fabric attachments if the fabric begins to sag, lean, or otherwise not present a sufficient barrier to access. |
B. Fencing: 1. Protection fencing shall be equal to the following: b. PLASTIC MESH FENCE: With permission from the project arborist or UW Campus arborist heavy-duty orange plastic mesh fencing fabric 48 inches wide may be substituted under certain conditions. Fencing shall be attached to metal “U” or “T” post driven into the ground of sufficient depth to hold the fabric solidly in place without sagging. The fabric shall be attached to the post using attachment ties of sufficient number and strength to hold up the fabric without sagging. The Owner’s Representative may request, at any time, additional posts, deeper post depths, and/or additional fabric attachments if the fabric begins to sag, lean, or otherwise not present a sufficient barrier to access. |
| PART 3 - EXECUTION -> 3.01 SITE EXAMINATION AND COORDINATION | A. Forward all consulting arborist reports to the University of Washington project manager and the University of Washinton Campus Arborist. | None |
| PART 3 - EXECUTION -> 3.02 TREE AND PLANT PROTECTION AREA | B. Preparation: 6. Any work to prepare the tree protection area according to project arborist report shall follow the general requirements and limitations for operations within the tree protection area as outlined in SECTION 3.02.G.1. In general: hand tools only, and no materials, equipment, compaction or spoils within the Tree Protection Area. |
No previous language for item 6 |
| PART 3 - EXECUTION -> 3.02 TREE AND PLANT PROTECTION AREA | A. Protection of existing trees and shrubs: 3. Protection fencing shall be located at the area indicated by the consulting arborist report. Generally the protection fencing shall be located at the Critical Root Zone (CRZ). The area equal to one (1) foot radius for every inch diameter from a tree measured at Diameter Standard Height (DSH). i. Paint the corners of the tree protection fence with an orange line indicating the extent of the fence location for accurate replacement in the case the fence is moved (with permission from the project arborist). Maintain the paint marks until the tree protection is removed. |
No previous language for item 3-i |
| PART 3 - EXECUTION -> 3.04 TREE AND STUMP REMOVAL | A. Tree Removal: 6. Conduct a site walk with the Carpenter Shop representative to indicate the exact location of the log placement. Logs without tree numbers will be removed by the contractor at no expense to the University of Washington. 7. Arrange logs in the log placement area with all the tree tags or number markings on the right side of the horizontal log pile. Do not stack logs more than 3 feet high. |
None |
Custodial, Mailing & Waste
| Section | Item revision/addition | Previous language |
|---|---|---|
| Title | Changed document name from "Building Maintenance" to "Custodial, Mailing & Waste" standards | |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 2. Provide electrical outlets at one side of building entrances and at stair landings. See the Wiring Devices section of the Electrical Standards document for further outlet design info. 3. Provide weatherproof electrical outlets and hose bibs at building parapets every 75 ft. o.c. for maintenance and window washing. Provide separate circuits for outlets. |
5. Miscellaneous Building Utility Services b. Provide electrical outlets per Electrical-Wiring Devices at one side of entrances and at stair landings. c. Provide weatherproof electrical outlets and hose bibs at building parapets at 75 ft. o.c. for maintenance and window washing. Provide separate circuits for outlets. |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 4. Avoid placing wood flooring or wood steps in interior building design. UW custodial staff cannot maintain flooring and the sponsoring department will need to contact an outside contractor to refinish the floors. | None |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 5. Concrete steps in interior buildings shall have a finish to prevent stains. Do not incorporate bare concrete steps in interior building design. (Finished concrete steps are acceptable.) | None |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 6. Provide glass whiteboards for all new and replacement whiteboard installations. | None |
| D. Custodial -> Design Criteria -> General Building Design - Custodial Servicing | 7. Avoid interior slip-resistant metal grates in vestibules, building entrances and walk-off areas as they are difficult for custodial staff to maintain. | None |
| D. Custodial -> Design Criteria -> Custodial Closets -> Bulk Supply Closet | The following additions apply to each custodial closet type and are in each custodial closet section: - Provide mechanical exhaust with more than 10 air changes per hour (ACH). Consult the Mechanical and EH&S Laboratory and Ventilation Standards. - All storage rooms for waste containers and chemical cleaning products shall have non-recirculating exhaust systems to minimize contamination of adjacent rooms. |
None |
| D. Custodial -> Design Criteria -> Custodial Closets | The following additions apply to the Equipment Closet, and Primary and Supplemental Working Closets: - Provide two water fixtures at custodial closets – one faucet at the mop sink level for bucket filling, and one mounted higher for soap feed connection (hose bibb acceptable for upper fixture). - Provide an eyewash station with a dedicated drain per the EH&S Emergency Washing Equipment requirements. |
None |
| D. Custodial -> Design Criteria -> Custodial Closets -> Equipment Closet | 1. Provide an Equipment Closet 200 s.f. room for storage of bulk equipment. 2. Provide a pair of out-swinging doors, 60 inches wide, minimum. 3. Provide 16-inch deep adjustable shelving with heavy duty brackets to the ceiling, full length at the longest wall. 4. Provide 8 GFCI electrical outlets on its own dedicated circuit with a dedicated EMT conduit homerun. Outlets to be dual plug and spaced throughout the room to allow space for large equipment charging. Mounting height 36”. 5. All storage rooms for waste containers and chemical cleaning products shall have non-recirculating exhaust systems to minimize contamination of adjacent rooms. 6. Provide mechanical exhaust with more than 10 air changes per hour (ACH). Consult the Mechanical and EH&S Laboratory and Ventilation Standards. 7. Provide a center floor drain and floor-mounted custodial sink with splash shield located adjacent to door. 8. Provide two water fixtures at custodial closets – one faucet at the mop sink level for bucket filling, and one mounted higher for soap feed connection (hose bibb acceptable for upper fixture). 9. Provide an eyewash station at the floor sink location. 10. Provide mop hanger/drying rack adjacent to sink by Bobrick or approved substitution. 11. Do not locate closet within restrooms. 12. Do not locate pipe chases or utility panels within closet. |
None |
| D. Custodial -> Design Criteria -> Custodial Closets -> Primary and Supplemental Working Custodial Closets | 1. Provide a Primary Working Closet - a 120 s.f. (10’. x 12’) room at one per 25,000 to 30,000 s.f. of floor area assigned to custodial department. 2. Provide Supplemental Working Closets sized 70 to 80 s.f. (10’ x 7’ or 8’) on floors that do not include a Primary Working Closet. Each floor shall have at least one Primary or Supplemental Working Closet. In major buildings and renovations, alternate between Primary and Supplemental Working Closets by floor, based on the total number of floors and the area requirements for Primary closets. Supplemental Working Closets shall also be provided in historical building renovations or smaller building renovations where a Primary Working Closet cannot be provided. |
2. Primary Working Custodial Closet a. Provide 120 s.f. (10’. x 12’) room at one per 25,000 to 30,000 s.f. of floor area assigned to each custodian. |
| D. Custodial -> Design Criteria -> Custodial Dispatch Office | 1. Provide a Custodial Dispatch Office for projects 300,000 g.s.f. or more. Consult with the custodial unit about space requirements. | Provide for specific projects. Coordinate with Project Manager and Custodial Services |
| E. Restrooms -> Design Criteria | Hand Drying 1. Provide one wall-mounted hand dryer per every two sinks in multi-stall and single-occupancy restrooms (required unless patient care area). Reference the preferred manufacturer list or contact the custodial department for product specifications. 2. Do not incorporate both hand dryers and paper towel dispensers in multi-stall restroom design. |
None |
| E. Restrooms -> Design Criteria | Soap Dispensers 1. Provide one wall-mounted soap dispenser per every two sinks in multi-stall restrooms. Contact the custodial unit for product specifications. See Preferred Manufacturer List. 2. Do not incorporate countertop-mounted/deck-mounted soap dispensers in design. |
None |
| E. Restrooms -> Design Criteria | Waste Containers 1. Restroom waste containers are separate and free-standing. Consult with UW Recycling for product specifications. 2. Do not incorporate grommets / trash drops in restroom counter design or recessed waste containers into walls. |
None |
| E. Restrooms -> Design Criteria | Menstrual product dispensers 1. One menstrual product dispenser must be installed in all-gender restrooms and restrooms designated for female students. This is to adhere to Washington state law (RCW 28B.170.010), that requires higher education institutions to provide free menstrual products in these restrooms. Please see preferred manufacturer list for preferred dispenser. |
None |
| E. Restrooms -> Design Criteria | Restroom stalls 1. Provide a menstrual product/sanitary napkin disposal container in each stall in all-gender and women’s restrooms. See Preferred Manufacturer List 2. Magnetic rigid doorstops must be installed on the inside of each restroom stall, to improve ergonomics of custodial staff servicing the stalls. Please consult the preferred manufacturer list for product. |
None |
CAAMS Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 1 | A. The University of Washington has an existing campus-wide access control system. This system is known as the “Campus Automated Access Management System” (CAAMS). Principal components of CAAMS are provided by Lenel and Life Safety Power. All components and devices must be sourced through UW CAAMS Integrator under the Terms and Conditions of the current sole source Contract. | A. The University of Washington has an existing campus-wide access control system. This system is known as the “Campus Automated Access Management System” (CAAMS). Principal components of CAAMS are manufactured by Lenel, a unit of United Technologies Corporation. |
| PART 2 - PRODUCTS -> 2.01 MANUFACTURERS | A. Access control intelligent controllers, input modules, output modules and Reader interface modules shall be provided as Lenel part numbers by the CAAMS contractor under the terms of the current UW sole source contract. No substitutions are acceptable. | A. Access control intelligent controllers, input modules, output modules and card readers shall be branded by Lenel and use Lenel part numbers. No substitutions are acceptable. |
| PART 2 - PRODUCTS -> 2.02 thru 2.07 | Updated model numbers for Lenel controllers and modules | - |
| PART 2 - PRODUCTS -> 2.14 thru 2.16 | Updated manufacturer and model numbers and specifications for multi-technology card readers | - |
| PART 2 - PRODUCTS -> 2.17 REQUEST-TO-EXIT (REX) MOTION DETECTOR | D. REX motion detectors shall not be required at doors whose lock hardware includes a built-in request-to exit switch. A separate, local audible sounder shall be required on the secure side of the entry. | D. REX motion detectors shall not be required at doors whose lock hardware includes a built-in request-to exit switch. |
| PART 2 - PRODUCTS -> 2.21 COMPOSITE CABLE | B. Provide Lake Connect Air # WSECRFI-2832.5. No substitutions are acceptable. | B. Provide Lake Cable Part #S16C4E-06RFIConnect Air # WSECRFI-2832.5. No substitutions are acceptable. |
| PART 2 - PRODUCTS -> 2.22 WIRELESS LOCKSETS & 2.23 WI-FI LOCKSETS | 2.22 WIRELESS LOCKSETS A. Wireless locksets may be used on interior doors on a case-by-case basis as approved by the CAAMS Manager. In no case shall wireless locksets be used on building exterior doors. B. Wireless locksets shall be self-contained lockset units that provide stand-alone access control capability at the door. Wireless locksets shall include card reader, electric lock, door position switch, and request-to-exit device. C. Wireless Lockets can be assigned Unlock schedules in CAAMS D. Use Allegion AD400 series locks. No Substitutions. E. All Part Numbers must be approved by the CAAMS manager, sourced with Lenel Part Numbers through the UW CAAMS integrator. 2.23 WI-FI LOCKSETS A. WI-FI locksets may be used on interior doors that DO NOT require a CAAMS unlock schedule and must be approved on a case-by-case basis as approved by the CAAMS Manager. a. Typical locations include mech rooms, IT closets, mail rooms etc. B. WI-FI Locksets shall be self-contained lockset units that provide stand-alone access control capability at the WI-FI locksets shall include card reader, electric lock, door position switch, and request-to-exit device. C. Use Corbin IN120 platform only – No Substitutions. D. All Part Numbers must be approved by the CAAMS manager, sourced with Lenel Part Numbers through the UW CAAMS integrator. |
(previous 2.22 WIRELESS LOCKSETS section replaced with new 2.22 and 2.23 sections) |
| PART 3 - EXECUTION -> 3.02 INTELLIGENT CONTROLLER PANEL INSTALLATION | A. Install each panel at CAAMS plywood backboards in equipment closet locations as indicated. B. Install each panel at a location and height to facilitate ease of service. C. Identify each panel name and enclosure with a permanent marking label installed on the exterior cabinet door. D. Neatly dress and tie all wiring within the enclosure and wire management gutters using Velcro ties. Do not obstruct access to terminal strips and configuration jumpers with wiring. E. Provide terminating resistor on all unused input connections. F. Label all inputs and outputs wiring with a permanent marking sleeve label. G. Ground all shielded cables in accordance with manufacturer’s instructions at the panel enclosures. H. Trim and wrap all unused shield wires to prevent shorting or inadvertent grounding at remote device boxes. Use heat shrink sleeving. |
A. Install each panel at CAAMS backboards in equipment closet locations as indicated. B. Install each panel at a location and height to facilitate ease of service. C. Identify the software and hardware address of each panel with a permanent metal marking label installed on the exterior of the cabinet. D. Neatly dress and tie all wiring within panel. Do not obstruct access to terminal strips and configuration jumpers with wiring. E. Provide terminating resistor on all unused input connections. F. Label all inputs and outputs with a permanent marking label. G. Ground all shielded cables in accordance with manufacturer’s instructions. H. Trim and wrap all unused shield wires to prevent shorting or inadvertent grounding. |
| PART 3 - EXECUTION -> 3.03 CONNECTIONS TO CAMPUS NETWORK | B. Contractor shall provide connections between data outlets and Intelligent Controller and power supply network interface module. Device patch cords shall be factory terminated with appropriate length cables. Keep excess length to absolute minimum. C. Other types of security systems (video surveillance systems, intrusion alarm systems, etc.) shall not be connected to the CAAMS VLAN. D. Other types of security systems (video surveillance systems, intrusion alarm systems, etc.) share CAAMS horizontal pathways or door riser conduits. |
B. Contractor shall provide connections between data outlets and Intelligent Controller and power supply network interface module. C. Other types of security systems (video surveillance systems, intrusion alarm systems, etc.) shall not be connected to the CAAMS VLAN. |
| PART 3 - EXECUTION -> 3.04 POWER SUPPLY INSTALLATION | A. All CAAMS Access Control boards shall be installed in Life Safety Enclosures at the CAAMS Panel head end backboard. Do not install remote power supplies to support local door hardware without approval from CAAMS Manager. | A. Install all system power supplies at Intelligent Controller panel backboard locations as indicated. Do not install power supplies at other locations. |
| PART 3 - EXECUTION -> 3.05 CARD READER INSTALLATION | D. Use Screw wire terminations at inside reader locations. Use Pigtail wire terminations at exterior locations. | None |
| PART 3 - EXECUTION -> 3.06 CONNECTION TO ELECTRIC LOCK HARDWARE | A. Use plug and play connectors when connecting to electrified locking hardware. Crimp pins to field wiring and use correct conductor housings to match. Avoid additional splice points. | None |
| PART 3 - EXECUTION -> 3.09 CONNECTION TO ELEVATORS | B. Install an Elevator Demarcation panel adjacent to all elevator machine rooms. Including future integrations. | None |
| PART 4 - Backboard Layouts -> 4.01 GENERAL | A. Changes to the backboard layout or location required by site conditions must be reviewed and approved by the CAAMS manager. B. Install all equipment in accordance with manufacturer’s instructions and approved shop drawings. C. Traka Cabinets shall not be installed in publicly accessible spaces. Ideally they will be in a room that has Wi-Fi or Wireless card reader. |
None |
| PART 4 - Backboard Layouts -> 4.02 & 4.03 | Added backboard detail and image | - |
EH&S - Emergency Washing Equipment
| Section | Item revision/addition | Previous language |
|---|---|---|
| 1. Applications | Typical areas on the University campus where EWE is needed include the following: c. Areas with closed systems, particularly those under pressure, that can catastrophically fail and cause the chemicals to leak including the power plant, shops, and mechanical rooms. 1) For closed-loop hydronic systems and cooling towers, EWE is required at the location of the chemical pot feeders or chemical feed tanks. For new installations, provide utility sink at eyewash location. |
No previous language for item c-1 |
EH&S - Laboratory Ventilation
| Section | Item revision/addition | Previous language |
|---|---|---|
| B. General Laboratory Ventilation | 3. Design the air change rate for each laboratory room to provide the following: a) Adequate make-up air for LEV including fume hoods and bio-safety cabinets. b) Adequate tempering for personal comfort and laboratory requirements c) As a general guideline, wet labs should be designed for a minimum of 6 air changes per hour (ACH) and dry labs for a minimum of 3 ACH. Air change rates must be determined based on specific room hazards and reviewed on a case-by-case basis. All laboratory air change rates shall be reviewed and approved by EH&S. |
No previous language for item 3-c |
| G. Laboratory Renovations General Design and Commissioning | Summary: Added section G which includes requirements for laboratory renovations and commissioning. Contains: – Requirement for project engineers to review code history and applicable risk assessments with EH&S and the client for renovations involving existing lab systems, and to document code compliance changes in the project requirements. – Requirement to comply with SEFA standards for laboratory furniture and finishes, including performance testing and certification of chemical resistance. – Requirement to comply with national standards and best practices (e.g., ANSI Z9.5, CDC, NFPA, WISHA, NIH, OLAW, etc.). – Requirement for the Project Manager to identify subject matter experts (e.g., fume hoods, BSCs, hazardous storage) during design and collect full inventories of hazardous materials and lab equipment to be used or stored. – Lab chemical inventories must be shown on design drawings. – Requirement that relocated fume hoods and ducted Type B2 biosafety cabinets be recertified, and that associated HVAC systems be rebalanced to restore safe airflow and containment conditions, with EH&S confirmation required before use. – Commissioning plan must be developed during design and include ventilation validation procedures, system flow specs, test and balance reports, ASHRAE 110 documentation for fume hoods, and a tracking system for deficiencies. – Fume hood flow alarms must be calibrated to alarm at ±10% of the designed capture velocity. – Biosafety cabinets must be certified to NSF 49 by an independent contractor prior to use. – Emergency eyewashes and showers must be certified to meet UW and ANSI Z358.1 standards. |
None |
EH&S - Safe Access and Maintainability
| Section | Item revision/addition | Previous language |
|---|---|---|
| 3. Location and maintenance of equipment and components | Window washing shall be designed and constructed to be performed using passive fall protection e.g., working from the ground, finished floor or platform with standard guardrails. Where passive fall protection is not deemed safe and/or feasible, active fall protection systems (e.g., rope descent systems, personal fall arrest systems) can be designed and constructed with a supporting Safe Access Plan and approval from the UW Building Services Department. Refer to the Roof and Building Envelope section of the Requirements Common to All Disciplines and Projects document for instructions on the required Safe Access Plan. | Window washing shall be designed and construction to be performed from the ground, finished floor or platform with standard guardrails. |
UW Recycling (under Services, Custodial & Recycling)
| Section | Item revision/addition | Previous language |
|---|---|---|
| Whole document | "UW Recycling" document moved from Exterior Improvements tab to the Services, Custodial & Recycling tab |
February
Facilities Design Standard - Variance Request and Decision Process
| Section | Item revision/addition | Previous language |
|---|---|---|
| All | Added passages such as Design Standards from Other Units, Safety and Access Issues. Added language to Resolution Process and a Step by Step Guide to the Decision Process |
Variance Request Process Flow Chart
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added new document "Variance Request Process Flow Chart" to visually display the process of Variance Requests |
Mechanical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design Criteria -> Design Criteria | 6. Do not use motorized shades and windows unless in auditoriums, lecture halls or large instructional spaces. Consider passive design strategies instead. a. For auditoriums with motorized shades and windows, do not install diffusers at the base of the window. |
None |
| C. Air Handlers and Ventilation Fans -> Design Criteria | 1. Provide filtered and conditioned mechanical ventilation supply to all occupied building spaces on the UW campus, including but not limited to office, classroom, library, dining, patient care, laboratory, or housing occupancies and elsewhere where required by code or programmatic needs. | 1. Provide filtered and conditioned mechanical ventilation supply to all office, classroom, library, dining, patient care, laboratory, or housing occupancies and elsewhere where required by code or programmatic needs. |
| C. Air Handlers and Ventilation Fans -> Design Criteria | 2. Size air handler to provide at least 20% additional ventilation (outdoor) air volume above system design. | None |
| E. Hydronic Systems | Merged 3 sections (Building Chilled Water Systems, Hydronic Coils, Hydronic Heating) into 1 consolidated "Hydronic Systems" section | |
| E. Hydronic Systems -> Freeze Protection and Chemical Management | 1. Provide inhibited propylene glycol for systems subject to freezing. a. Provide 25% glycol concentration. |
None |
| E. Hydronic Systems -> Hydronic Coils | 5. Size coils at no more than 450 feet per minute face velocity. | 5. Size coils at no more than 550 feet per minute face velocity. |
| E. Hydronic Systems -> Building Chilled Water Systems -> Programming | 2. All new cooling systems shall be connected to the central utilities CCW system. Discuss the intent of using Central Cooling Water with Engineering Services before design begins. | 2. Discuss the intent of using Central Cooling Water with Engineering Services before design begins. Using the campus system is encouraged, but the CCW chillers and distribution piping may not have adequate capacity to serve new loads. |
| E. Hydronic Systems -> Building Chilled Water Systems -> Programming | 6. Size the cooling system with sufficient capacity to accommodate estimated future loads. Incorporate capacity control strategies to limit short-cycling and provide efficient operation during present and future loading. | 6. Size the chiller(s) with sufficient capacity to accommodate estimated future loads. Incorporate capacity control strategies to limit short-cycling and provide efficient operation during present and future loading. |
| E. Hydronic Systems -> Building Chilled Water Systems -> Chilled Water Design Criteria | 9. For systems that include an air/dirt separator, provide a removable head for maintenance, and isolation valves at both the inlet and outlet. a. Critical systems that must remain on at all times must have a bypass on equipment such as heat exchangers, air separators, and meters b. See Preferred Manufacturer List for preferred vendor. |
None |
| Mechanical -> Air/Dirt Separators | Spirovent Or approved Equal |
None |
| E. Hydronic Systems -> Hydronic Heating -> Hydronic Heating Design Criteria | 4. Reset converter and radiation water temperatures by the outside air temperature. Historically in existing buildings, the normal reset schedule for a converter is to reset the water temperature from 180 °F to 140 °F as the outside air temperature changes from 20 °F to 70 °F respectively. Consult with Engineering Services and HVAC shop on current operating conditions. | 4. Reset converter and radiation water temperatures by the outside air temperature. Historically in existing buildings, the normal reset schedule for a converter is to reset the water temperature from 180 °F to 140 °F as the outside air temperature changes from 20 °F to 70 °F respectively. The normal reset schedule for a radiation system is to reset the water temperature from 180 °F to 100 °F as the outside air temperature changes from 20 °F to 70 °F respectively. |
| G. Building Steam and Condensate -> Installation, Fabrication, and Construction | 6. Condensate shall drain to a receiver that is vented to atmosphere with horizonal piping sloped at a minimum of 1/4" per foot in mechanical rooms. This is especially important on domestic hot water heat exchangers where the load is highly variable and stall conditions are expected. | None |
| H. Refrigeration -> Design Criteria | 2. Do not use Variable Refrigerant Flow (VRF) systems for space cooling. 3. New systems that require a refrigerant leak detection system are not allowed. |
2. Use of Variable Refrigerant Flow (VRF) system for space cooling is strongly discouraged. a. VRF systems are not allowed if they require a refrigerant leak detection system. b. Provide suitable isolation valves on each branch circuit. |
| H. Refrigeration -> Design Criteria | 11. Microchannel coils are discouraged for larger sized air-cooled chillers. Discuss with Engineering Services if microchannel coils will be used on a project. | None |
| H. Refrigeration -> Design Criteria | 12. Provide factory applied anti-corrosion coating for all condenser coils. | None |
| H. Refrigeration -> Design Criteria | Removed refrigerant detection alarm signage display item. It is redundant with EH&S "Refrigeration Machinery Room Design and Construction" document | g. Provide all refrigerant audible and visual devices with signs permanently hung below the device(s). Signs must be three-layer etched plastic with white letters on a blue background. Letters must be a minimum of ½” high. h. Signs within the refrigerant machinery room must read: WHEN FLASHING REFRIGERANT LEAK / NO FAN EXIT SPACE Signs outside each refrigerant machinery room entrance must read: WHEN FLASHING REFRIGERANT LEAK / NO FAN DO NOT ENTER SPACE |
| H. Refrigeration -> Design Criteria -> Refrigerant Machinery Rooms | Added "Refrigerant Machinery Rooms" subsection under Refrigeration -> Design Criteria section. Moved RMR items from Refrigeration section, and consolidated section with EH&S "Refrigeration Machinery Room Design & Construction" | |
| H. Refrigeration -> Design Criteria -> Refrigerant Machinery Rooms | f. Leak detection system alarm level must be set and calibrated to the refrigerant’s Permissible Exposure Limit (PEL). | e. Leak detection system alarm level must be set to the refrigerant’s Permissible Exposure Limit (PEL). Where calibration gas is not available at the PEL, set the alarm level for the lower calibration gas level. For example, adjust the set point to 900-ppm when the PEL is 1000-ppm, if 1000-ppm calibration gas is not available. |
| K. Potable and Nonpotable Water -> Design Criteria | 9. Design lab HW circulation pipes (140 degrees) with flow velocity not to exceed 3 FPS. a. Confirm the capacity of lab HW based on user needs and discuss with Engineering Services. |
9. Design lab HW circulation pipes (140 degrees) with flow velocity not to exceed 3 FPS. |
| K. Potable and Nonpotable Water -> Design Criteria | 14. For laboratory buildings, size domestic water heater to support 1 emergency shower and 1 emergency eyewash station in addition to regular non-emergency loads. See EH&S Emergency Washing Equipment document for all requirements. | None |
| K. Potable and Nonpotable Water -> Design Criteria | 15. Provide floor drain directly below eyewash station discharge, or locate eyewash station at sink. See EH&S Emergency Washing Equipment document for all requirements. | None |
| K. Potable and Nonpotable Water -> Design Criteria | 16. For Laboratory buildings, provide vacuum breakers for all lab faucets. | None |
| K. Potable and Nonpotable Water -> Design Criteria | 18. Provide electronic sensor faucets for all lavatories. Provide an outlet and transformer under the sink. Provide a minimum of two 24V transformers for all lavatories with 2 or more sinks. Coordinate with electrician for installation. See Electrical Design Standards for outlet and transformer requirements. | 18. Provide electronic sensor faucets for all lavatories. |
| K. Potable and Nonpotable Water -> Design Criteria | 19. Provide manual flush valves. Do not use electronic sensor flushometers for toilets and urinals. | 19. Do not use electronic sensor flushometers for toilets and urinals. |
| K. Potable and Nonpotable Water -> Design Criteria | 20. Unless otherwise specified by code, provide the following flow rates: a. Water Closets = 1.28 gpf b. Urinals = 0.125 gpf c. Public Lavatories = 0.5 gpm d. Residential Lavatories = 1.2 gpm e. Showers = 1.5 gpm f. Kitchen Faucet = 1.8 gpm g. Metering faucets = 0.25 gpc |
20. Unless otherwise specified by code, provide the following flow rates: a. Water Closets, Dual Flush = 1.28/ 1.1 gpf b. Urinals = 0.125 gpf c. Public Lavatories = 0.5 gpm d. Residential Lavatories = 1.2 gpm e. Showers = 1.5 gpm f. Kitchen Faucet = 1.8 gpm g. Metering faucets = 0.25 gpc |
| K. Potable and Nonpotable Water -> Design Criteria | Removed | 21. Hard wire electronic fixtures from facility power source. |
| K. Potable and Nonpotable Water -> Design Criteria | 29. Provide non-electronic thermostatic mixing valves. See Preferred Manufacturer List. a. Operate water heaters and storage tanks at 140°F. |
30. Provide non-electronic thermostatic mixing valves. See Preferred Manufacturer List. |
| R. Metering and Gauges -> Meter Installation | 4. Provide a list of all meters and communication/connectivity requirements. | None |
| S. Motors and Variable Frequency Drives (VFDs) -> Variable Frequency Drives | 14. See Preferred Manufacturer List for VFD model requirements. | None |
| Mechanical -> VFDs (for Building Applications) | Danfoss VLT FC-102 ABB ACS800 No substitutions |
Allen Bradley Powerflex 70 Danfoss VLT FC-102 Yaskawa GPD 506 No substitutions |
| Mechanical -> VFDs (for Central Utilities Applications) | Yaskawa Industrial Drives No substitutions |
Yaskawa GPD 506 |
| U. Piping, Valves, Pressure Testing, and Accessories -> Products, Material and Equipment -> Pipe -> Pipe Code P-5 (table) | ** All Natural gas service to buildings shall be equipped with a seismic shutoff valve located on the exterior of the building. | None |
Architectural
| Section | Item revision/addition | Previous language |
|---|---|---|
| C. Interiors -> Construction (C10) -> Interior Door Standard Specifications -> 1.04 Application notes | Removed | 2. Fire Rated Door: Mineral Core Fire Doors are unacceptable. Where 45, 60, or 90 Minute Rated Doors are required, provide Hollow Metal Doors. |
| Gender Inclusive Restroom Design Guidelines | Changed language from "gender neutral" to "gender inclusive" | |
| Gender Inclusive Restroom Design Guidelines | URINALS 1. Use of urinals in Gender Inclusive Restrooms: When urinals are included in gender-inclusive restrooms, they must be enclosed within a stall partition to ensure privacy and accommodate a variety of users. 2. Clear Signage: The restroom must have clear signage indicating that urinals are present, both within the restroom itself (near the urinals) and at the entry to the restroom. This ensures users are aware of the restroom's facilities before entering. |
Urinals will not be allowed in multi-user gender neutral restrooms. |
Civil
| Section | Item revision/addition | Previous language |
|---|---|---|
| N. Ground Disturbance and Utility Locates | Replaced previous Ground Disturbance and Utility Locates section with newer SOP |
Electrical
| Section | Item revision/addition | Previous language |
|---|---|---|
| V. Lighting -> Basis of Design -> Design Criteria - Interior Lighting | 3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star). • Fixtures shall be the type that LED lamp array assembly can be replaced without having to replace the entire fixture. • For non-dimming, use Type B fixture, single-ended option, direct voltage (277V or 120V) • For dimmable, use type C, 0-10V. 120V is preferred. • Proprietary drivers are not allowed. • Fixtures shall not have plastic components that will melt or deform from heat generated by the fixture. • LED DALI drivers are required. |
3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star). • Fixtures shall be the type that LED lamp array assembly can be replaced without having to replace the entire fixture. • For non-dimming, use Type B fixture, single-ended option, direct voltage (277V or 120V) • For dimmable, use type C, 0-10V. 120V is preferred. • Proprietary drivers are not allowed. • Fixtures shall not have plastic components that will melt or deform from heat generated by the fixture. |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 3. Do not use wireless systems. Any wireless systems must have prior approval from Engineering Services and shops. | 3. Wireless systems may be considered for renovation projects when the installation of conduit and wiring is not able to be used. Wireless systems needs approval from UW Facilities. 4. Control systems that utilized batteries for devices and other equipment are not acceptable. |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 6. Provide BacNet connection for future integration to the Building Automation System (BAS). | 6. Provide BacNet connection to the Building Automation System (BAS). |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 12. Provide UPS whereas to protect the lighting control circuit boards inside the lighting control panels. | None |
| Electrical -> Network Lighting Control Systems | Legrand Cooper Or approved equal |
Crestron Douglas Lutron |
Irrigation
| Section | Item revision/addition | Previous language |
|---|---|---|
| Products, Materials and Equipment | 1. Controllers: a. Calsense CS3000, 8 to 48 station capacity with transient surge protector (part #TP-100), to tie into existing central control system, with one of the following hardware options: Ethernet capability, CS3-EN-10/100 Mbps. Ethernet is preferred, Cellular, CS3-GR-KIT, can be used where Ethernet is unavailable. No exceptions. |
1. Controllers: a. Calsense CS3000, 8 to 48 station capacity, to tie into existing central control system, with one of the following hardware options: Ethernet capability, CS3-EN-10/100 Mbps. Ethernet is preferred, Cellular, CS3-GR-KIT, can be used where Ethernet is unavailable. No exceptions. |
| Products, Materials and Equipment | 7. Irrigation Deduct Water Meter: Krohne. See Preferred Manufacturer List for irrigation deduct meter requirements. | 7. Irrigation Deduct Water Meter: See Preferred Manufacturer List for irrigation deduct meter requirements. |
| Products, Materials and Equipment | 23. Wye Strainer: Zurn/Wilkins SXL a. If POC is downstream of building wye strainer, secondary strainer is not necessary |
None |
| Installation, Fabrication and Construction | 9. Seal sleave ends with servicable duct tape or bunched filter fabric to prevent soil intrusion (before and after install). | None |
| Installation, Fabrication and Construction | 13. Locate automatic control valve boxes within the irrigation zone, do not cluster valve boxes. | None |
| Installation, Fabrication and Construction | 15. Automatic control valve boxes shall be placed in the irrigation zone they serve. Do not cluster automatic control valve boxes together. Locate valve boxes orthogonally to adjacent features. | None |
| Installation, Fabrication and Construction | Removed all drip irrigation details | |
| Exterior Improvements - Irrigation -> Wye Strainer | Wye Strainer Zurn/Wilkins SXL Or approved equal |
None |
CAD & BIM Standards
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added zip folder of title block template sheets for download | None |
Room Numbering Standards
| Section | Item revision/addition | Previous language |
|---|---|---|
| Floor Numbering, & Structure of Room Nomenclature | Adjusted Mezzanine labeling |
EH&S - General Requirements for Laboratories
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added new document, "General Requirements for Laboratories" to guide laboratory design, including building and lab requirements, hazardous materials handling, egress, and some electrical and utility requirements |
EH&S - Seismic Securement Requirements
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added new document "Seismic Securement Requirements" for requirements for seismic securements of non-structural components in buildings. |
EH&S - Refrigeration Machinery Room Design & Construction
| Section | Item revision/addition | Previous language |
|---|---|---|
| Design Requirements -> 7. Refrigerant Detection and Alarm Systems | c. The refrigerant Leak Detection System shall be compatible with and connect to the building Fire Alarm System and the Building Automation System for purposes of audible and visual alarms and for communicating with the central monitoring service for the building. | c. The refrigerant Leak Detection System shall be compatible with and connect to the building Fire Alarm System for purposes of audible and visual alarms and for communicating with the central monitoring service for the building. |
| Design Requirements -> 7. Refrigerant Detection and Alarm Systems | t. Sequence of operations During normal operation, the refrigerant detection system commands the supply and exhaust fans to normal occupied airflow rate. i. Upon an alarm condition, the refrigerant detection system notifies the FACP which commands the ventilation system to the emergency exhaust and supply volumes. Transmit an alarm signal to building fire alarm system and the Building Automation System. The refrigerant detection system audible and visual alarms are activated by the FACP. ii. The building fire alarm system and the Building Automation System monitor normal exhaust and supply speed fan(s) status via current sensing relays. During failure of fan(s) to operate at normal speed in normal mode, a trouble signal at both the Fire Alarm System and the Building Automation System. Fans shall default to the emergency airflow rate. The audible and visual notification devices are activated. iii. The Fire Alarm System and Building Automation System monitor emergency speed fan(s) status via current sensing relays. During failure of fan(s) to operate at emergency airflow rate in emergency mode, generate a supervisory signal at the Fire Alarm System. The audible and visual alarms are activated. iv. The Fire Alarm System monitors leak detection panel status via a trouble contact. During failure of leak detection panel, generate a trouble signal at the Fire Alarm System. Upon panel failure, fan(s) default to emergency airflow rate. The audible and visual alarms remain inactivated. | t. Sequence of operations During normal operation, the refrigerant detection system commands the supply and exhaust fans to normal occupied airflow rate. i. Upon an alarm condition, the refrigerant detection system notifies the FACP which commands the ventilation system to the emergency exhaust and supply volumes. Transmit an alarm signal to building fire alarm system and the Building Automation System. The refrigerant detection system audible and visual alarms are activated by the FACP. ii. The building fire alarm system and the Building Automation System monitor normal exhaust and supply speed fan(s) status via current sensing relays. During failure of fan(s) to operate at normal speed in normal mode, a trouble signal at both the Fire Alarm System and the Building Automation System. Fans shall default to the emergency airflow rate. The audible and visual notification devices are activated. |
August
Mechanical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design criteria -> Operational Constraints | 4. Do not install equipment in difficult to access locations. If unavoidable, see the Maintenance Access Plan for Hazardous Spaces section of the General Information and Common Requirements document. | 4. The installation of equipment in challenging-to-access spaces (such as atria, high ceiling areas, or confined spaces) must have a "maintenance access plan" included in the design design documents and drawing details. The plan must be reviewed and approved by the maintenance and repair staff at ES and UW shops. The plan should note at minimum the following: potential hazards, hazardous areas and a plan to mitigate safety risks in these areas, tasks to be performed in these areas, necessary equipment, and the responsible party for purchasing and storing equipment. A JHA template must be filled out before ordering equipment, with the Shop responsible for maintenance, and submitted with Closeout Documents. A link to access and download the JHA template can be found on this Job Hazard Analysis site. Additional JHA examples can be provided upon request. |
| D. Building Chilled Water Systems -> Design Criteria | 1. Establish project design criteria for the following items: l. Compliance with current and upcoming refrigerant regulations. Discuss maintenance and reporting requirements to regulatory agencies with Engineering Services. |
1. Establish project design criteria for the following items: l. Carbon footprint. |
| D. Building Chilled Water Systems -> Design Criteria | 16. Provide a chemical pot feeder with filtration, coupon rack and make-up water meter on each building chilled water system not directly connected to campus CCW. | 16. Provide a chemical pot feeder, coupon rack and make-up water meter on each building chilled water system not directly connected to campus CCW. |
| J. Hydronic Heating -> Design Criteria | 10. Provide a chemical pot feeder with filtration, coupon rack and make-up water meter on each hydronic heating system. | 10. Provide a chemical pot feeder, coupon rack and make-up water meter on each hydronic heating system. |
| Y. Water Treatment and Flushing -> Design Criteria | 11. Provide a chemical pot feeder with filtration, a coupon rack, and a make-up water meter for each hydronic system, (except chilled water system not decoupled from the CCW). | 11. Provide a chemical pot feeder, a coupon rack, and a make-up water meter for each hydronic system, (except chilled water system not decoupled from the CCW). |
| F. Coils and Filters -> Filters | 3. Avoid custom filter sizes that are difficult to source. Square filters are preferred (eg. 12x12, 20x20, 24x24 etc.) | 3. Avoid custom filter sizes that are difficult to source. |
| F. Coils and Filters -> Filters | 7. Include Magnehelic pressure gauges across all AHU filter banks. | 7. Include pressure gauges on MERV 13 filters for air intakes above 500 cfm |
| F. Coils and Filters -> Filters | 8. Provide disposable filters instead of washable or reusable filters where possible. | None |
| H. Refrigeration -> Products, Materials and Equipement | 2. See Preferred Manufacturer List for VRF A/C and heat pump manufacturers. | None |
| I. Ductwork and Duct Pressure Testing -> Mounting | Removed | 1. For roof-mounted ductwork, fans and air handlers, see the architectural standard drawing titled Mechanical Equipment Mounting for minimum mounting height . |
| L. Potable and Nonpotable Water -> Design Criteria | 8. Design domestic hot water circulation (120 degrees) piping with flow velocity not to exceed 4 feet per second (FPS). | 8. Design hot water circulation piping with flow velocity not to exceed 4 feet per second (FPS). |
| L. Potable and Nonpotable Water -> Design Criteria | 9. Design lab HW circulation pipes (140 degrees) with flow velocity not to exceed 3 FPS. | None |
| L. Potable and Nonpotable Water -> Water Header Configurations for Lab and Non-Lab Buildings | Change made to Lab Building Water header diagram - moved irrigation connection downstream of RPBP at building entry point | |
| N. Waste and Drains -> Installation, Fabrication and Construction | Electronic Trap Primers - added "Precision Plumbing Products (PPP) model Prime-Time" to Preferred Manufacturer List | None |
| O. Water Reclaim System -> Reclaimed Water Usage | 4. Design consultant for water reclamation system must have American Rainwater Catchment Systems Association (ARCSA) certification. | None |
| Q. Environmental Control Systems -> Hardware and Software | 6. Third party equipment that integrates with the BAS shall be BACnet Testing Laboratory (BTL) certified. | None |
| Q. Environmental Control Systems -> Graphic Display | 6. Freeze-stat shall be non-averaging type and installed upstream of the cooling coil. | 6. Freeze-stat shall be averaging type and installed upstream of the cooling coil. |
| V. Piping, Valves, Pressure Testing, and Accessories -> Products, Material and Equipment | Table Pipe Code P-1: Below grade: Copper Type K with brazed fittings or ductile iron; |
Table Pipe Code P-1: Below grade: Copper Type K or ductile iron; |
| V. Piping, Valves, Pressure Testing, and Accessories -> Products, Material and Equipment -> Strainers | 1. Provide wye type strainers in 3-inch and smaller piping. 3. Provide basket type strainers in piping larger than 3-inch, except for steam piping. |
1. Provide wye type strainers in 2-inch and smaller piping. 2. Provide basket type strainers in piping larger than 2-inch, except for steam piping. |
| V. Piping, Valves, Pressure Testing, and Accessories -> Products, Material and Equipment -> Gaskets | 1. Gaskets shall not contain asbestos. | None |
| W. Pumps -> Products, Material and Equipment | 3. Provide de-coupled frame-mounted pumps for motor sizes greater than 1hp. 4. In-line circulators may be used up to 1hp when they can be adequately supported and are easily accessible. 5. Ensure entire pump case can be insulated for chilled water applications. |
3. Provide close-coupled pumps up to 1-hp; otherwise provide a frame-mounted type. 4. In-line circulators may be used when they can be adequately supported and are easily accessible. 5. Provide frame-mounted, not close coupled, chilled water pumps, so that the entire casing and connections may be completely insulated. |
| W. Pumps -> Products, Material and Equipment | Preferred Manufacturer List - Added Domestic & Lab HW Pump preferences: Grundfos Bell & Gossett |
None |
| W. Pumps -> Installation, Fabrication and Construction | 7. Pump alignment should be conducted by qualified manufacturer’s representative during startup. Submit alignment data to owner for approval. | 7. Verify pump alignment and submit alignment data. |
| Y. Water Treatment and Flushing -> Installation, Fabrication and Construction | 6. For closed-loop hydronic systems, provide a phenolic label that indicates total water volume (in gallons) near chemical pot feeder, and document in O&M manual. 7. Where glycol feed tanks and/or chemical pot feeders are used, provide a phenolic label at the feed tank that reports system volume, the glycol type and concentration (in %). |
6. For closed-loop hydronic systems, label total water volume (in gallons) and glycol concentration (in %) near chemical pot feeder and O&M manual. |
Civil
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. General -> Montlake Landfill | For projects located east of Montlake Boulevard, all design proposals shall address specific local challenges and must be approved by Engineering Services. Key concerns include but are not limited to settlement issues, which can impact the slope of piping. This is particularly problematic around connections between individual buildings and central campus utility systems. Consultants shall discuss any anticipated issues with ES prior to approval. | None |
| N. Ground Disturbance and Utility Locates | Prior to any ground disturbance at the UW Seattle Campus, it is mandatory to initiate a utility locate by calling 811. For inquiries regarding this process, contact the Building and Utility Shutdowns and Utility Locates Manager at 206-543-7158 or kd79coop@uw.edu. Buried facilities may be present under roads, sidewalks, lawns, and planting beds. A utility locate is required to ensure any publicly or University owned underground lines are identified and marked, enabling safe excavation and avoidance of the lines. This practice is crucial to prevent not only damage to utility lines, but also property damage and personal injuries that could result from breaking a line. Compliance with locate requirements is legally mandated for all excavation activities, ranging from planting bulbs or flowers to large-scale excavations for building foundations. The University of Washington adheres to the WA State Dig Law and Industry Best Practices. Additional mandatory protocols include: • Maintaining an up-to-date LIVE utility map for the project. • Ensuring that shutoffs for all systems potentially impacted by excavation activities remain accessible. In the event of any utility strike, regardless of severity, immediate notification is required – contact the Seattle Campus Building and Utility Shutdowns and Utility Locates Manager. Contractors and vendors must also notify their University of Washington contract manager. Detailed Process Overview: 1. Locate request is submitted to 811, generating a time-stamped ticket. 2. Ticket is sent to all relevant utilities and facilities within the defined locate polygons, which include the main campus, UW Hospital, ICA, west campus, among others. 3. If a locate is necessary the appropriate shop or utility provider is notified. This may include the UW High Voltage Shop, Irrigation Shop, BIT, Heavy Equipment Shop, Zone Electricians, Shop 24, construction and project managers, and the UW locate contractor. 4. The UW locate contractor marks the UW water distribution, sewer, storm drains, low voltage, chilled water, steam, and natural gas systems. 5. Following marking, the Building and Utility Shutdowns and Utility Locates Manager verifies at the job site that all University facilities are correctly marked. This completes UW’s responsibility as a facility owner. 6. The ticket is updated to reflect the completion of marking for UW facilities. Note that additional utilities such as Seattle City Light, Seattle Public Utilities, Seattle Department of Transportation, Puget Sound Energy, Metro, Lumen, and numerous fiber providers may also be present on our property. |
None |
Electrical
| Section | Item revision/addition | Previous language |
|---|---|---|
| B. Design criteria -> Operational Constraints | 4. Do not install equipment in difficult to access locations. If unavoidable, see the Maintenance Access Plan for Hazardous Spaces section of the General Information and Common Requirements document. | None |
| E. Automatic Transfer Switches (ATS) -> Products, Materials and Equipment | 1. Russelectric, ASCO, or approved equal: a. UW Class E1 and E2 emergency services. b. Bypass/Isolation (BIS) style transfer switches. 2. Russelectric, ASCO, or approved equal: a. UW Class E3 and E4 emergency services. b. Outlying UW Campuses, and other remote facilities. c. Bypass/isolation (BIS) not required. d. For each project, transfer switches shall be of the same manufacturer. |
1. Russelectric, no exception: a. UW Class E1 and E2 emergency services. b. Bypass/Isolation (BIS) style transfer switches. 2. Russelectric, and other manufactures pre-approved by Engineering Services: a. UW Class E3 and E4 emergency services. b. Outlying UW Campuses, and other remote facilities. c. Bypass/isolation (BIS) not required. d. For each project, transfer switches shall be of the same manufacturer. |
| N. Power Layout and Provisions -> Installation, Fabrication and Construction -> Typical Building Power Distribution Riser Diagram | Add note to diagram “5.) For distribution feeders, provide main breakers in panels on distribution risers” | None |
| P. Panelboards -> Basis of Design -> Design Criteria | 1. Panelboards are not allowed for main building service entrance equipment in UW Class N1, N2S, and N2P type services. 2. Panelboards may be used for UW Class N3 services with approval from UW Engineering Services and UW High Voltage Shop. Panelboards for this application shall be front accessible and utilize group mounted thermal-magnetic molded case circuit breakers. Load Centers are not acceptable. |
1. UW Class N3 services building panelboards shall be front accessible and utilize group mounted thermal-magnetic molded case circuit breakers. Load Centers are not acceptable. 2. For UW Class N1, N2S, and N2P services building panelboards, provide electronic trip units with long time, short time and ground fault (LSG) protection for molded case circuit breakers. Instantaneous protection shall not be provided since it limits coordination with downstream molded case circuit breakers. Two and preferably three levels of ground fault protection are desired. Selectivity is critical to the University in order to limit the extent of power outages. |
| P. Panelboards -> Basis of Design -> Design Criteria | 3. Panelboards for multi-floor building risers shall have main circuit breakers. | None |
| P. Panelboards -> Basis of Design -> Design Criteria | Removed | 7. Provide “service entrance” listed service entrance applications. |
| V. Lighting -> Basis of Design | 3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star) • Fixtures shall be the type that LED lamp array assembly can be replaced without having to replace the entire fixture. • For non-dimming, use Type B fixture, single-ended option, direct voltage (277V or 120V) • For dimmable, use type C, 0-10V. 120V is preferred. • Proprietary drivers are not allowed. • Fixtures shall not have plastic components that will melt or deform from heat generated by the fixture. |
3. All interior fixtures are required to be LED fixtures. LED luminaires are required to be vetted by the Design Light Consortium (DLC or Energy Star) |
| V. Lighting -> Basis of Design | 6. Color temperature shall be 3500K, except 4000K in hospital or clinical areas or unless otherwise specified or approved by Engineering Services and Electricians. Other locations, included but not limted to: • Living areas (dorms) • Sales locations (bookstore) • Art displays |
6. Do not use proprietary drivers. |
| V. Lighting -> Basis of Design | 11. Access to the luminaires must be considered in design. In auditoria and high bay areas access to fixtures shall use fixture lowering systems. Access requiring scaffolding is prohibited. Refer to Design Criteria section for Job Hazard Analysis requirements in challenging-to-access spaces. | 10. Review with consultant/contractor during luminaire selection installation and maintenance approaches. |
| V. Lighting -> Basis of Design | 3. In general, pathway lighting in the UW Seattle campus is required and shall be reviewed and approved by the UW Landscape Committee and Engineering Services. Pathway lighting shall be high cutoff. | 3. In general, pathway lighting in the UW Seattle campus are required to match the performance and appearance of the Archetype series AR/SAR by KIM lighting. Other types of light fixtures will need review and approval by the UW Landscape Committee and Engineering Services. |
| V. Lighting -> Basis of Design | 4. All street and walkway lighting shall have waterproof overcurrent protection, placed at each pole base and fused based on the connected load. | 4. Protect all street and walkway luminaires with waterproof in-line fuse holders located in each pole base. |
| V. Lighting -> Basis of Design | 5. All new or modified street and pathway lighting conductors shall be installed in conduit and an additional 1.25” conduit should be installed for future control conductors. Direct buried cable is not acceptable. Provide a hand hole for each light pole to allow for access to wire terminations and fuses. | 5. All new or modified street and pathway lighting conductors shall be installed in conduit and an additional 1.25” conduit should be installed for future control conductors. Direct buried cable is not acceptable. |
| V. Lighting -> Basis of Design | 6. Where 3 or more power conduits enter a pole, provide a hand hole at the base. | None |
| V. Lighting -> Basis of Design | Removed | 6. Fuses are required to be on the line side of the driver. 7. Repair or module replacement shall be accomplished quickly and without tools. The entire module is required to snap out without tools, and to include quick-disconnect plugs on all wiring. Allow for a new module to be quickly inserted to eliminate downtime. 8. The lens frame is required to be removable without tools, providing easy lens replacement in the event that breakage occurs. Require the door frame to be prevented from lifting out of its hinges when hanging in the down position. |
| V. Lighting -> Submittals | 4. Shop drawing as-builts are required for final delivery to UW Records including accurate topoloy and labeling of all devices. | 4. Shop drawing as-builts are required for final delivery to UW Records. |
| V. Lighting -> Products, Materials and Equipment | Removed | 2. Sockets and screw in base luminaires are preferred. |
| V. Lighting -> Installation, Fabrication and Construction | Removed | 1. Design louvers and lenses to open easily, hang open from the luminaire, and be removed from the luminaire, all without the use of tools. |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 5. Provide data connections as required to the FacNet system. Provide data connections for lighting control server integration including licensing via the secure Facilities Network (FacNet). | 5. Provide data connections as required to the FacNet system. |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 10. Provide Graphics User Interface to show light fixture status, controlled outlets and remote programming. | 10. Provide Graphics User Interface to show light fixture status and remote programming. |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 11. Provide service 120v outlet within 5ft of Lighting controller interface. | None |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 12. Provide public network port with Facnet port next to Lighting controller Brain | None |
| W. Lighting Control -> Basis of Design -> Design Criteria - Interior Lighting Control | 13. Label all wiring on both ends with length of wire and downstream device and upstream device designations. | None |
| W. Lighting Control -> Submittals | 2. Provide all documentation of the final commissioning report, lighting control one-line and wiring diagrams of all lighting control equipment. | 2. Provide documentation of the final commissioning report for lighting control. |
| W. Lighting Control -> Submittals | 3. All verified locations of control components, devices, remote drivers and all other control equipment shall be identified on final delivered one-line diagrams. All equipment should be easy to locate on drawings and diagrams. | None |
| W. Lighting Control -> Submittals | 4. Provide final software programming backup file. Coordinate delivery of the file with the zone lead electricians to ensure proper storage. | None |
| W. Lighting Control -> Submittals | 5. All main brain or room controllers are to be installed in electrical rooms and not in ceiling. | None |
| W. Lighting Control -> Submittals | 6. Provide all proprietary troubleshooting devices for installed lighting control systems used by proprietary lighting technicians, i.e. networking discovery devices, etc. | None |
| FF. Clock and Bell Systems | Added new 3 page Clock and Bell section | None |
Irrigation
| Section | Item revision/addition | Previous language |
|---|---|---|
| Basis of Design | 30. Irrigation Mockups and Dedicated MEP Irrigation Pre-Installation Meetings: a. Provide permanent, in-place mockups of each initial irrigation assembly for review and approval by the project team (consisting of the contractor, relevant trade partners, architects, engineers, the owner’s rep, and owners end users) prior to installing additional assemblies including: i. solvent welding ii. control wire splices iii. dedicated trace wiring for mainline and each zone iv. Irrigation sleeves v. Sleeve seals vi. gate valve assemblies (part 1 without enclosure, part 2 with enclosure and backfill) vii. automatic control valve assemblies (part 1 without enclosure, part 2 with enclosure and backfill) viii. quick coupler valve assemblies (part 1 without enclosure, part 2 with enclosure and backfill) ix. sprinkler assemblies (part 1 without enclosure, part 2 with enclosure and backfill) x. tree bubblers (part 1 without enclosure, part 2 with enclosure and backfill) b. Provide dedicated pre-installation meetings prior to installing the irrigation point of connection assembly, controller, and pipe and low voltage pathways and envelope penetrations and seals. |
None |
| Products, Materials and Equipment | c. Controllers shall have electrical metallic tubing (EMT) conduit connections. | None |
| Installation, Fabrication and Construction | 14. Landscape and irrigation inspections and performance testing – provide landscape and irrigation inspections and performance testing for review and approval by the project team at key milestones including subgrade, irrigation mainline and lateral pressure testing, finish grade including soil tapers at hardscapes, irrigation coverage testing, trees and plants upon delivery, trees and plants upon installation, mulching. | None |
| Installation, Fabrication and Construction | 15. The Contractor shall meet with the project team consisting of the contractor, relevant trade partners, architects, engineers, the owner’s rep, and owners end users to review/evaluate final irrigation system installation prior to final acceptance. | 15. The Contractor shall meet with the UW Irrigation representative, the Utility Engineer and UW Grounds Maintenance Manager to review/evaluate final irrigation system installation prior to final acceptance. |
Requirements Common to All Disciplines and Projects
| Section | Item revision/addition | Previous language |
|---|---|---|
| General information | Reorganizing - Moving general and "welcome" info to the FDS website page. This includes a welcome/introduction statement, FDS organization info, disclaimers, etc. Renamed document title to "Requirements Common to All Disciplines and Projects" instead of "General Information and Common Requirements" |
|
| A. Safe Access -> Maintenance Access Plan for Hazardous Spaces | Do not install equipment in difficult to access locations. If unavoidable, the installation of equipment in challenging-to-access spaces (such as atria, high ceiling areas, or confined spaces) must have a "maintenance access plan" included in the design documents and details. The plan must be reviewed and approved by the maintenance and repair staff at ES and UW shops. The plan should note at minimum the following: potential hazards, hazardous areas and a plan to mitigate safety risks in these areas, tasks to be performed in these areas, necessary equipment, and the responsible party for purchasing and storing equipment. A JHA template must be filled out before ordering equipment, with the Shop responsible for maintenance, and submitted with Closeout Documents. A link to access and download the JHA template can be found on this Job Hazard Analysis site. Additional JHA examples can be provided upon request. | None |
| D. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems -> Background Information | Rephrased, reorganized, and clarified previous Background Information section | |
| D. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems -> Design Process and Information | During the design phase of capital projects, documentation to track IoT/OT building automation systems and devices shall be obtained by filling out the specified columns in the Early Building Services (EBS) sheet of the UW-IT Outlet Schedule spreadsheet. The template linked is an example of this sheet. IP addresses for IoT/OT devices will not be issued without this information. The EBS sheet shall be updated when IoT/OT systems and devices for buildings are introduced and added, during the design, construction, and commissioning phases of the project. The information required in the EBS shall include the following: |
Early in the design phase of capital projects, documentation to track IoT/OT and digital systems information shall be established. The document shall be updated when IoT/OT and/or internet connected digital systems for buildings systems are introduced and added, during the design, construction, and commissioning phases of the project. The information to be provided shall include the following: |
| D. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems -> Design Process and Information | Removed requirements to document/track the listed previous language | • The serial number of each device. • Firmware version information & identification of the currently most recent available firmware version. • A list of minimally required ports/services for each device. • Confirmation that no additional ports/services are active on each device. • Confirmation from the vendor that the IoT system does not have any software libraries with known vulnerabilities; including but not limited to those on the TCP/IP Stack Library Vulnerabilities page, maintained by the UW CISO’s office https://ciso.uw.edu/iot/iot-resources/tcp-ip-stack-library-vulnerabilities/ • Digital photo of each device once installed in its final location. • Enterprise network connectivity document, which may include but is not limited to: o TCP/UDP ports & protocols used by the devices o External server IPs that need connectivity to these devices (if applicable) o How devices authenticate on the network • Lifecycle information for the IoT system: o End of Life / End of Sale (EOL / EOS) date o End of Development (EOD) date o End of Service Life / End of Support (EOSL) date • Ownership information: o Name of system owner o Name(s) of systems admin(s) |
| D. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems -> Design Process and Information | Added documentation Requirements: - Deliver user guide if owner's manual does not include - Vendor job number (if different than PDG) - BacNet device ID *BACnet should be disabled by default unless it is needed. If BACnet is needed, the provisioning of a BACnet Device Instance ID shall be coordinated with the UW Facilities OT Team and the UWF Environmental Control Systems Manager (ECSM) (Shop 69, 206-685-8869 or 206-543-4208)). The use of Device Instance IDs not provided through coordination with the UW Facilities OT Team and theECSM is prohibited. |
None |
| J. Sustainability | The University is committed to sustainability at a leadership and policy level as stated in the following - • Climate Action Plan, 2009 • Executive Order No.13, 2012 • Campus Master Plan, 2019 • Sustainability Action Plan, 2020 • STARS Reporting Ongoing (developed by the national Association for the Advancement of Sustainability in Higher Education) • Salmon-Safe standards |
The University is committed to sustainability at a leadership and policy level as stated in the following - • Climate Action Plan, 2009 • Executive Order No.13, 2012 • Campus Master Plan, 2019 • Sustainability Action Plan, 2020 • STARS Reporting Ongoing (developed by the national Association for the Advancement of Sustainability in Higher Education) |
| K. Security Assessment | Security Assessment Prior to design of a project, the UW Owner’s Representative and Design Team shall reach out to UW Police at uwpolice@uw.edu to do a project security assessment (see below) to incorporate into the scope of the project. Any items not included in the scope of work should be sent to uwf-am-pm@uw.edu UWPD Project Security Assessments can include but is not limited to – • Project security elements of the design (CPTED review; Crime Prevention Through Environmental Design) • Identify available security and safety integration elements (I.e. security detection and alerting devices; and/or security cameras, and/or security barriers, etc..) • Identifying available safe-locations, able to meet criteria as Safe Room(s) and/or Safe Haven status. |
None |
Room Numbering Standards
| Section | Item revision/addition | Previous language |
|---|---|---|
| Floor Numbering | Replaced "Floor Numbering" table with more detailed and stringent language. Important change of note is that Ground floor labeling/numbering is the baseline for all other floor labels and superscedes all other floor tags |
Title Block
| Section | Item revision/addition | Previous language |
|---|---|---|
| Added Title Block Template PDF document to CAD and BIM with drawing page labeling requirements |
CAD and BIM Standards
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Standards, PDF Requirements, and Compliance Review Submittals -> CAD Standards | d. Title blocks shall follow the Title Block Template and must contain the following information: i. Record Drawing Date ii. UW Project Number iii. UW Facility Number (FACNUM) iv. UW Project Name v. Sheet Name vi. Sheet Number vii. A Key Plan viii. List of Revisions ix. Consultant Company Name e. Floor and room numbering shall be according to Room Numbering Standards |
d. Title blocks must contain the following information: i. Record Drawing Date ii. UW Project Number iii. UW Facility Number (FACNUM) iv. UW Project Name v. Sheet Name vi. Sheet Number vii. A Key Plan viii. List of Revisions ix. Consultant Company Name |
Trees – Additional Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Trees -> Part 0 – PRE CONSTRUCTION AND SITE PLANNING -> 0.01 SITE PLANNING | 3. An evaluation of the existing trees on a site is required prior to design. This evaluation will be conducted by a third-party Arborist for projects costing greater than 10 million. Send data in spreadsheet (excel) format to the UW Campus arborist. | 3. An evaluation of the existing trees on a site is required prior to design. This evaluation will be conducted by a third-party Arborist for projects costing greater than 10 million. |
| PART 3. EXECUTION | 5. Send tree removal list to the Campus Arborist and Fine Carpentry shop as soon as possible. The carpenters will indicate which trees to salvage for the UW Salvage Wood Program. Conduct a site walk with the UW Carpenter representative and/or the UW Campus Arborist to indicate which log lengths and species can be utilized. In general, logs requested have a minimum diameter of 14” and a preferred length of 13 feet (some logs can be as short as 4’). The carpenters will indicate which trees they would like and any variances on the size dimensions. For instance, smaller unique trees may be requested due to their species or growth habit. i. If a tree tag is present, nail the tag to the end of the cut log. If no tag is present, write the tree number on the end of each log with spray paint or grease pen. |
None |
Preferred Manufacturer List
| Section | Item revision/addition | Previous language |
|---|---|---|
| Mechanical -> VFDs | Danfoss VLT FC-102 | Danfoss VLT 20X |
| Electrical -> Bells | Edward Signalling Cat. No. 1065-N5 Buzzers | Simplex cat#2902-9501 Buzzers |
| Electrical -> Electrical Testing Contractor | Added 3 manufacturers: Shermco Group CBS Eaton |
Removed: Sigma 6 |
February
Mechanical
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. Design criteria -> Design Criteria | 15. Provide floor drains in all mechanical and water entry rooms. | None |
| A. Design criteria -> Inter-discipline Coordination | 4. Avoid piping in electrical and IT (ex. MDF & IDF) rooms. See Electrical Design Standard for more detail. | None |
| D. Building Chilled Water Systems -> Design Criteria | 18. Chilled water piping is not allowed in electrical and IT (ex. MDF & IDF) rooms. See Electrical Design Standard for more detail. | None |
| C. Air Handlers and Ventilation Fans -> Design Criteria | 10. Manifolded fume exhaust systems must have N+1 redundancy so they remain operational at design conditions during repair or unplanned outage. | None |
| H. Refrigeration -> Design Criteria | 3. Use of Variable Refrigerant Flow (VRF) system for space cooling is strongly discouraged. a. VRF systems are not allowed if they require a refrigerant leak detection system. b. Provide suitable isolation valves on each branch circuit. |
3. Use of Variable Refrigerant Flow (VRF) system for space cooling is discouraged |
| H. Refrigeration -> Design Criteria | 9. Gravity drain all condensate pans, discuss with Engineering Services if a condensate pump is required. | None |
| H. Refrigeration -> Products, Materials and Equipment | 1. Provide a minimum 3-year extended warranty beyond standard project warranty for compressors (parts and labor). | 1. Provide 5-year warranty option for compressors. |
| J. Hydronic Heating -> Design Criteria | 11. Any piping on the roof or exposed to freezing temperatures requires heat trace for freeze protection. Provide thermostatic control of heat trace wiring. | None |
| L. Potable and Nonpotable Water -> Design Criteria | 15. Provide wall mounted water closets | None |
| L. Potable and Nonpotable Water -> Design Criteria | 25. Monitor domestic and lab hot water supply temperature in the DDC. Discuss alarming with Engineering Services. | None |
| L. Potable and Nonpotable Water -> Design Criteria | 26. Provide non-electronic thermostatic mixing valves. See Preferred Manufacturer’s List. In PML: Leonard TM-1520B-LF-DT. No substitutions |
None |
| N. Waste and Drains -> Design Criteria | 11. Provide floor drains in all lavatories and connect to waste piping systems. | None |
| N. Waste and Drains -> Installation, Fabrication and Construction | 5. Floor drains: Slope floors to floor drains. Specify block-outs twice the size of the drain body and infill with non-shrink grout to prevent perimeter cracking at concrete. Provide electronic type trap primers for all floor drains. | 5.Floor drains: Slope floors to floor drains. Specify block-outs twice the size of the drain body and infill with non-shrink grout to prevent perimeter cracking at concrete. |
| N. Waste and Drains -> Design Criteria | 5. Do not install any type of chemical treatment system without first discussing with Engineering Services and the UW Environmental Health and Safety (EH&S) Department. | None |
| O. Water Reclaim System -> Water Reclaim and Rainwater Harvesting | 2. Given specialty equipment and maintenance requirements, include an equipment warranty period of 3 years at minimum. | None |
| O. Water Reclaim System -> Reclaimed Water Usage | 3. All designs that include water reclamation must have prior approval by Engineering Services. | None |
| Q. Environmental Control Systems -> Sensors | 4. Actuators – provide low voltage 24V actuators. a. Exception: Provide pneumatic actuators for all steam control valves. |
4. Actuators – provide low voltage 24V actuators. 5. Provide pneumatic rather than self-contained steam control valves on hot water converters. |
| Q. Environmental Control Systems -> Graphic Display | 10. Monitor hydronic closed loop makeup water flow rate, and incorporate an alarm which indicates a system leak. See Preferred Manufacturer List for make-up water meter standard. In PML: Badger Recordall disc series meter with HR-E LCD 4-20 Encoder, or approved equal |
10. Monitor hydronic closed loop makeup water flow rate, and incorporate an alarm which indicates a system leak. |
| Q. Environmental Control Systems -> Graphic Display | 11. Provide a means to exclude any "rouge" zones from temperature / pressure reset calculations using the front-end graphics. | None |
| Q. Environmental Control Systems -> Metering & Monitoring | 2. Do not use airflow measurement stations for control. TAB contractor should determine appropriate fan speed or damper position. | None |
| Q. Environmental Control Systems -> Metering & Monitoring | 3. Discuss with Engineering Services the use of water flow meters for control. | None |
| Q. Environmental Control Systems -> Sensors | 5. Freeze-stat and duct pressure safeties shall be manual reset (push button). | None |
| Q. Environmental Control Systems -> Sensors | 6. Freeze-stat shall be averaging type and installed upstream of the cooling coil. | None |
| Q. Environmental Control Systems -> Sensors | 7. Any fan safeties including but not limited to freeze-stat, duct pressure safeties, and duct smoke detector shut down signal shall be hard-wired to fan safety circuit. | None |
| Q. Environmental Control Systems -> Sensors | 8. Provide a Magnehelic gauge and a digital differential pressure transducer across each filter bank and monitor through the DDC. | None |
| Q. Environmental Control Systems -> Sensors | 9. Do not use CO2 sensors for AHU level control. CO2 sensors are acceptable at the zone level to comply with energy code requirements. | None |
| Q. Environmental Control Systems -> Sensors | 10. Thermostats should not be occupant adjustable. | None |
| Q. Environmental Control Systems -> Deliverables | 3. The final as-built control drawings should include a Bacnet network diagram including third party devices. | None |
| V. Piping, Valves, Pressure Testing, and Accessories | Coil Condensate CD P-1 Hydrostatic (1) In accordance with UPC – Min. 10 ft. head. |
Piping System: Coil Condensate Symbol: CD Pipe Code: P-1 Pipe Test Method: Hydrostatic Test Pressure: 60 lb/in^2 |
| V. Piping, Valves, Pressure Testing, and Accessories | Test Pressure: (1) In accordance with UPC – Min. 10 ft. head. | Piping System: Trap Primer Symbol: TP Pipe Code: P-1 Pipe Test Method: Hydrostatic Test Pressure: 150 lb/in^2 |
| V. Piping, Valves, Pressure Testing, and Accessories | 1. Pressure test all pipe systems to maintain constant pressure for a minimum of 2 hours. 2. Test piping after all associated fittings, and valves have been installed. 3. Demonstrate to an Owner representative for each pressure testing. Leave the pipe exposed and do not insulate until the associated pipe section has been signed off by an Owner representative. 4. Repair leaks discovered during pressure testing, and retest. |
1. Pressure test all pipe systems. 2. Test piping after all associated fittings, and valves have been installed. 3. Demonstrate to an Owner representative for each pressure testing. Leave the pipe exposed and do not insulate until the associated pipe section has been signed off by an Owner representative. 4. Repair leaks discovered during press |
| R. Identification | 1. Labels to be permanent weatherproof adhesive type. | None |
EH&S - Emergency Washing Equipment
| Section | Item revision/addition | Previous language |
|---|---|---|
| 2. Equipment | To encourage shower use and prevent flooding, provide showers with stalls equipped with a sloped floor or shower pan, plumbed floor drain, and privacy curtain. | To encourage shower use and prevent flooding, EH&S strongly recommends installing showers with stalls equipped with sloped floor or shower pan, plumbed drain, and privacy curtain. |
CAAMS
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. CAAMS -> Basis of Design | All types and size of projects should include providing CAAMS on all of the following areas: o Stairwell doors o Elevators o Exterior doors o Public spaces o Operational spaces identified by space owner |
None |
CAAMS Standard Specifications
| Section | Item revision/addition | Previous language |
|---|---|---|
| PART 1 - GENERAL -> 1.05 BASIC DESCRIPTION OF SYSTEM | C. CAAMS Head End power supplies and enclosures shall be installed in a dedicated closet with connecting raceways to horizontal cable trays and building risers. Pathways and risers to be determined as part of system design by CAAMS system Integrator. | None |
| PART 2 - PRODUCTS -> 2.23 KEY CABINETS | 2.23 KEY CABINETS A. All University keys to be secured via Traka Intelligent Key Cabinets. |
None |
| PART 3 - EXECUTION -> 3.13 KEY CABINETS | 3.13 KEY CABINETS A. All new buildings and major renovations shall provide Traka Intelligent Key Cabinets as part of each project. These cabinets shall be used to secure all UW keys issued to the General Contractor and its sub-contractors for use during the discovery phase and the project itself. B. No UW keys to leave Campus. All keys to be secured in the cabinet and accounted for at the end of each shift. C. Setup and access shall be coordinated with the UW Building Access Group. D. A permanent secure location for the Traka Intelligent cabinet shall be identified during project design. Cabinet shall be relocated to its permanent location for Building Management use as part of the T2O process. |
None |
Irrigation
| Section | Item revision/addition | Previous language |
|---|---|---|
| Basis of Design | 29. Irrigation systems must be designed and installed for year round use without winterizing. Specified covered depths should satisfy this requirement. Any atypical covered depths, must be approved in advanced and will require direct bury rated insulation to emulate R-value for 12” of soil depth for laterals, and 18” of soil depth for main line. | None |
| Basis of Design | 30. Although most irrigation scope resides within the scope of the landscape architect, and possibly an irrigation designer sub-consultant, there is a critical minority irrigation scope that requires multi-disciplinary collaboration with other consultants and trade partners, including but not limited to: a. All disciplines shall design with safe access for irrigation appurtenances and equipment are installed per code, between 2 and 5 feet above finished floor, and in a serviceable condition. b. Electrical for 120v dedicated circuits for fixed equipment to irrigation controllers, ethernet and Wi-Fi controllers, pathways through building and penetrations through building envelope, and heat trace tape and insulation for freeze protection on irrigation pipes where necessary with approval for atypical applications, c. Plumbing for mechanical room point of connection downstream of master meter and upstream of building domestic pressure regulation valve, irrigation header assembly, irrigation piping distribution through building and penetrations through building envelope, irrigation pressure zones for multi-level buildings and/or booster pumps, and freeze protection insulation on irrigation pipes where necessary with approval for atypical applications. d. Architectural for pathways for low voltage control wire through building and penetrations through envelope, for on-structure roof drainage, for freeze protection insulation on irrigation pipes where necessary with approval for atypical applications, for roof safe access and fall protection, and easy access via non-program spaces to ingress and egress irrigation and planting related products. e. Structural for roof safe access and fall protection. |
|
| Products, Materials, and Equipment | 1. Controllers: a. Calsense CS3000, 8 to 48 station capacity, to tie into existing central control system, with one of the following hardware options: Ethernet capability, CS3-EN-10/100 Mbps. Ethernet is preferred, Cellular, CS3-GR-KIT, can be used where Ethernet is unavailable. No exceptions. b. Calsense controllers and enclosures: for wall mount installation, use the Calsense wall mounted gray box. Use the Calsense Heavy‐Duty Stainless-Steel enclosure (pedestal) where wall mount is not applicable |
1. Controllers: Rain Master Evolution DX2, 6 to 48 station capacity, to tie into existing central control system, with flow/weather board (DX-FLOW), and one of the following hardware options: Ethernet circuit board (DX-ETHER-SM), phone board (DX-PH), or a radio circuit board (DX-RF). Ethernet is preferred, phone can be used where Ethernet is unavailable, and radio can be used where Ethernet and phone are unavailable. Radio communication requires the following additional requirements. A Radio Site Survey shall be conducted and passed by an authorized Rain Master representative. Provide a radio communication board (DX-RF), data radio (EV-RADIO-F) and a low gain antenna (EV-ANT-FD) for line of site, or a high gain antenna (EV-ANT-F) for non line of site applications. No exceptions. |
| Products, Materials, and Equipment | 5. Table of model sizing, see Irrigation standards | See Irrigation standards |
| Products, Materials, and Equipment | 11. Ball valves: Spears TU2000 Blocked True-union Ball Valve. No Substitutions. | 11. Ball valves: KBI Low Torque slip-by-slip, or approved substitution. |
| Products, Materials, and Equipment | See Irrigation Standards | 13. Sprinkler heads - See Irrigation Standards |
| Products, Materials, and Equipment | 14. Alternate Water Delivery Media: a. Tree watering bags – Uses may include remote plantings, and/or in lieu of a dedicated tree zone comprised of conventional irrigation. |
14. Alternate Water Delivery Media: a. RainBird IS Series Irrigation Supplement: Non-polymer time release microbial-activated water gel, with approval – Uses may include remote plantings, and/or in lieu of a dedicated tree zone comprised of conventional irrigation. |
| Products, Materials, and Equipment | 20. Do not use Drip Irrigation on any systems. | 20. Drip Irrigation: a. Drip Zones: Use RainBird PEB Series valves with RainBird in-line pressure regulators sized for zone GPM and pressure requirements of 40 psi. Minimum design zone flow to be 0.5 GPM. b. Drip Zone Filters: Amiad with 155 mesh (100 micron) filter, or approved substitution, correctly sized to support zone flow/GPM. For multiple valves requiring drip filters, use a primary filter on the irrigation header assembly sized to accommodate maximum system flow (largest zone at maximum pressure plus a quick coupler valve operating simultaneously at 20GPM), with approval. For example, Amiad steel filters for interior installations (e.g. 2-inch, 120 mesh/130 micron screen rated for 150 psi with steel housing, product number 2-200-1150-1013) or plastic filters for exterior installations (e.g. 2-inch T-S). Set horizontally installed filter at a 45 degree angle to the side; situate the valve box sideways and provide extensions as necessary to provide for filter serviceability. c. Drip Line: Toro DL-2000 RGP pressure regulating series drip line, no exceptions. For blank tube/no emitters use RainBird 1/2-inch solid tubing; solid tubing can be used as header/supply line in conjunction with 5/8-inch dripline or microline. d. Air Relief Valve: AVP-1 air vent in 6-inch round enclosure. Provide air relief valves to reduce soil ingestion. As a general application, install to avoid air locks. e. Flush Valve: Toro FCH-H auto flush in 6-inch round RainBird SEB-6X enclosure. f. Check valves: Use Hunter HC-50F-50F as required to reduce and/or equally distribute low line drainage. g. In-line PRVs: Use RainBird, rated 40 psi; size per zone flow. |
| Preferred Manufacturer List | New Preferred Manufacturer List added | None |
Electrical
| Section | Item revision/addition | Previous language |
|---|---|---|
| W. Lighting Control -> Products, Material and Equipment -> Interior/Classroom Lighitng Control Systems | 1. Approved manufacturers for building network lighting control systems: Legrand, Cooper, or approved equal. 2. All models from the above manufacturers shall be a 2-wire non-polarized system. |
1. Approved manufacturers for building network lighting control systems: Lutron, Legrand, Douglas. |
| V. Lighting -> Basis of Design -> Design Criteria - Exterior Lighting | 5. All new or modified street and pathway lighting conductors shall be installed in conduit and an additional 1.25” conduit should be installed for future control conductors. Direct buried cable is not acceptable. | None |
Structural
| Section | Item revision/addition | Previous language |
|---|---|---|
| A. General Requirements -> Design Live Load | Design Loading - Live and Super-Imposed Dead Load | Design Live Load |
| A. General Requirements -> Penetrations | Coordinate penetrations through structural members due to other trades. Sleeves shall be provided for penetrations and shall be 1” minimum larger than max penetration diameter. Penetrations required after structure is in place shall be reviewed and approved by Engineer of Record. | Coordinate penetrations through structural members due to other trades. Prior to any cutting or drilling contractor shall x-ray existing substrate for rebar and/or any other structural members, mark rebar locations on concrete, and use core drill not jack hammer to make holes. Should the existing rebars be damaged, contractor shall repair the existing rebars at no cost to the University. |
| B. Seismic Improvements and Building Modifications -> Seismic Studies | Seismic studies shall be submitted to Engineering Services for review and discussion at a design team meeting prior to issuing final report. Final report shall be issued no later than when drawings are submitted for permit issuance. | Seismic studies shall be submitted to Engineering Services for review and discussion at a design team meeting prior to issuing final report. |
| B. Seismic Improvements and Building Modifications -> Modifications to Existing Buildings | 5. Penetrations Prior to any cutting or drilling, contractor shall x-ray existing substrate for reinforcing and/or any other structural members. Reinforcing locations shall be marked on concrete. Penetrations shall be made by use of core drill not jack hammers. Should existing reinforcing be damaged, contractor shall repair the existing reinforcing at no cost to the University. |
None |
| D. Structured Floors and Roofs -> Vibration | 2. Maximum Vibration – Laboratory Buildings Provide key plans that clearly indicate design vibration criteria used for different areas. Basic design criteria is 2000 micro-inches/sec. maximum for lab areas. Refer to building program or specific equipment requirements for more restrictive vibration criteria. Provide vibration analysis report for lab or sensitive equipment areas with slow walking minimum in lab areas, slow walking in private corridors, and moderate walking in public corridors. Report shall be submitted to Engineering Services for review prior to issuing final report. Final report shall be issued no later than when drawings are submitted for permit issuance. |
2. Maximum Vibration Basic design is 2000 micro-inches/sec. maximum for lab areas. Refer to building program for more restrictive vibration criteria. Areas of some buildings may require 1000 micro-inches/sec. maximum. Use a walking speed of 100 steps per minute minimum. |
Architectural
| Section | Item revision/addition | Previous language |
|---|---|---|
| C. Interiors -> 1.02 Miscellaneous Hardware Requirements | A. Miscellaneous Lock Cylinders: Provide Cylinders, keyed to system, for Elevator Controls. Coordinate Cylinder and Cam types with equipment Elevator Manufacturer. B. Provide key cabinets integrated with UW CAAMS for Temp Key issuances. See CAAMS Standard Specifications for key cabinet requirements. Requirements to be agreed with UW Building Access Group. C. Key Pad Locksets: Schlage AD200 series, MTK keypad, RHO Trim |
A. Key Cabinet: Telkee AWC-250S. Confirm Capacity required with UW Lock Shop to secure department inventory. B. Miscellaneous Lock Cylinders: Provide Cylinders, keyed to system, for Elevator Controls. Coordinate Cylinder and Cam types with equipment Elevator Manufacturer. C. Provide Traka Key Cabinet integrated with UW CAAMS for Temp Key issuances. Requirements to be agreed with UW Building Access Group. D. Key Pad Locksets: Alarm Lock Trilogy DL3200/DL35003 |
| C. Interiors -> 1.02 Miscellaneous Hardware Requirements | E. Provide door closures on all doors leading to non-public spaces like mechanical and electrical rooms to help ensure that doors are not inadvertently left open. | None |
| D. Services -> Plumbing | 1. Drinking Fountains and Water Coolers a. All new drinking fountains shall have water bottle filling capabilities. b. When bi-level drinking fountains are installed, the bottle filling station shall be installed on the lower unit. c. See Preferred Manufacturer List – Mechanical for manufacturer requirements. |
1. Drinking Fountains and Water Coolers a. When bi-level drinking fountains are installed, the bottle filling station shall be installed on the lower unit. |
Plants
| Section | Item revision/addition | Previous language |
|---|---|---|
| Title | Plants & Trees - Standard Specifications A. Plants & Trees While this document provides comprehensive specifications applicable to both plants and trees, it should be noted that many tree-specific, additional specifications are addressed separately. For advanced tree-specific requirements not covered in this document, please refer to the 'Trees - Additional Specifications' document. |
Plants - Standard Specification |
| Part 1 - GENERAL -> 1.04 Quality Assurance | 7. Tree specification: See illustrations at the end of this document for information on tree rejections related to this section a. There shall be no roots greater than 1/10 diameter of the trunk circling more than one-third the way around in the top half of the root ball. Roots larger than this may be cut provided they are smaller than one-third the trunk diameter. There shall be no kinked roots greater than 1/5 the trunk diameter. Roots larger than this can be cut provided they are less than one-third the trunk diameter. See Container Root Structure and Ball and Burlap Root Structure b. Trees should be rooted in to the rootball so that soil or media remains intact and trunk and rootball move as one when lifted, but not root bound. The trunk should bend when gently pushed and should not be loose so it pivots at or below soil line. c. The point where the top-most root in the rootball emerges from the trunk shall be no deeper than one inch of the soil surface. d. The relationship between caliper, height and rootball size shall meet the ANSI Z60.1 standard or the Florida grades and standards for nursery stock. e. There should be one dominant leader to the top of the tree with the largest branches spaced at least 6 inches apart. Low branching trees should not have multiple dominant leaders. |
7. Tree specification: a. There shall be no roots greater than 1/10 diameter of the trunk circling more than one-third the way around in the top half of the root ball. Roots larger than this may be cut provided they are smaller than one-third the trunk diameter. There shall be no kinked roots greater than 1/5 the trunk diameter. Roots larger than this can be cut provided they are less than one-third the trunk diameter. b. Trees should be rooted in to the rootball so that soil or media remains intact and trunk and rootball move as one when lifted, but not root bound. The trunk should bend when gently pushed and should not be loose so it pivots at or below soil line. c. The point where the top-most root in the rootball emerges from the trunk shall be no deeper than one inch of the soil surface. d. The relationship between caliper, height and rootball size shall meet the ANSI Z60.1 standard or the Florida grades and standards for nursery stock. e. There should be one dominant leader to the top of the tree with the largest branches spaced at least 6 inches apart. |
| PART 3 - EXECUTION -> 3.03 INSTALLATION - PLANT MATERIALS | 1. Oversight: a. Project arborist shall be on-site on planting day to execute any needed pruning prior to planting or warranty plant replacements. The project arborist will inspect trees for damage and disease as outlined in Section 1.04 QUALITY ASSURANCE Section C. Best practice calls to limit structural pruning until after the 1st year, however, double leaders, dead/crossing branches or branches that will be in conflict (such as roads or pedestrians) should be addressed at planting. |
1. Oversight: a. Project arborist shall be on-site on planting day to execute any needed pruning prior to planting or warranty plant replacements. Best practice calls to limit structural pruning until after the 1st year, however, double leaders, dead/crossing branches or branches that will be in conflict (such as roads or pedestrians) should be addressed at planting. |
| PART 3 - EXECUTION -> 3.03 INSTALLATION - PLANT MATERIALS | d. If wire baskets are used to support the root ball, carefully remove the entire basket without allowing the root ball to fall apart. If the wire basket cannot be removed without damaging the root ball the project arborist may allow partial removal of the top and sides of the wire basket | None |
Trees
| Section | Item revision/addition | Previous language |
|---|---|---|
| Title | Trees – Additional Standard Specifications A. Trees This document shall be used in conjunction with the combined ‘Plant and Tree Standard Specifications’ to ensure a complete understanding and application of our standards for tree care. The specifications herein are intended to address specialized considerations and advanced management practices exclusive to trees. |
Trees – Standard Specifications |
| Part 0 - Pre Construction and Site Planning | FOR TREE PLANTING AND NEW TREES SEE “PLANTS-STANDARD SPECIFICATIONS” | None |
| Part 0 - Pre Construction and Site Planning -> Tree Removal Mitigation | 1. Tree mitigation a. Planned tree removals (Tree=any UW inventoried tree (regardless of size), any SDOT Right of Way tree, any tree over 6” DSH) i. Mitigation and planting 1. Replanting or Payment in lieu: 2 to 1 for all trees removed 2. 3 to 1 for all Trees of Distinction removed a. Excluding wildlife trees b. Excluding tree removals at the request of Grounds 2. A combination of replanting and payment in lieu of planting can be calculated by City of Seattle Replacement Cost as outlined in the SDCI Director’s Rule 8-2023, or UW Calculation of $1000 per tree, whichever is less. 3. Mitigation payments in lieu of planting is calculated and billed at substantial completion of the project. a. Example: 12 trees are removed for a project, 18 trees will be planted. The project owes $6,000 for offsite tree mitigation. |
1. Tree mitigation a. Planned tree removals (Tree=any UW inventoried tree (regardless of size), any SDOT Right of Way tree, any tree over 6” DSH) i. Mitigation and planting 1. 2 to 1 for all trees removed 2. 3 to 1 for all Trees of Distinction removed a. Excluding wildlife trees b. Excluding tree removals at the request of Grounds 3. Deficit mitigated @ $1000/tree a. Example: 12 trees are removed for a project, 18 trees will be planted. The project owes $6,000 for offsite tree mitigation. |
| Part 1 - General -> 1.03 Contractor Responsibility | 3. If, in the Owner’s sole opinion, replacement of damaged trees is determined not feasible or impractical, the full replacement costs shall be borne by the Contractor at values based upon the square inches of cross sectional area of trunk measured at standard height, in accordance with the following criteria: a. The assessed value of the tree using the Trunk Formula Method with a minimum value of $2500.00. b. Cost is doubled for Trees of Distinction (Exceptional, Historical, Memorial, Brockman Tour, Trees of Seattle) |
3. If, in the Owner’s sole opinion, replacement of damaged trees is determined not feasible or impractical, the full replacement costs shall be borne by the Contractor at values based upon the square inches of cross sectional area of trunk measured at standard height, in accordance with the following criteria: a. The assessed value of the tree using the Trunk Formula Method with a minimum value of $1000.00. b. Cost is doubled for Trees of Distinction (Exceptional, Historical, Memorial, Brockman Tour, Trees of Seattle) |
| Part 3 - Execution -> 3.02 Tree and Plant Protection Area | 1. In the event that construction activity is unavoidable within the Tree and Plant Protection Area, notify the Project Arborist who shall be onsite to monitor and advise on best practice tree protection. Submit a detailed written plan of action for approval. The plan shall include a statement detailing the reason for the activity including why other areas are not suited, a description of the proposed activity, the time period for the activity, and a list of remedial actions that will reduce the impact on the Tree and Plant Protection Area from the activity. Remedial actions shall include but shall not be limited to the following: | 2. In the event that construction activity is unavoidable within the Tree and Plant Protection Area, notify the Owner’s Representative and submit a detailed written plan of action for approval. The plan shall include a statement detailing the reason for the activity including why other areas are not suited, a description of the proposed activity, the time period for the activity, and a list of remedial actions that will reduce the impact on the Tree and Plant Protection Area from the activity. Remedial actions shall include but shall not be limited to the following: |
UWMC - Fire Alarm System 28 31 00
| Section | Item revision/addition | Previous language |
|---|---|---|
| 1.8 SUBMITTALS | 1. Prepare and submit electronic copies of shop drawings and catalog cut sheets and additional information required in this section, via the Construction Coordinator, to the A/E, UW Fire Protection Engineer and Fire Alarm Shop for Owner approval. | 1. Prepare and submit 6 copies of shop drawings and catalog cut sheets and additional information required in this section, via the Construction Coordinator, to the A/E, UW Fire Protection Engineer and Fire Alarm Shop for Owner approval. |
| 2.4 FIRE ALARM CONTROL PANELS (FACP) -> G. Notification circuits | 3. Visual notification circuits shall be synchronized at each FACP. | 3. Visual notification circuits shall be synchronized per circuit at each FACP. |
| 2.5 VOICE COMMUNICATION SYSTEM | A. Audio amplifiers shall be sized to provide ½ Watt minimum per attached audio speaker as shown on the drawings. Each audio amplifier shall have 50% minimum spare capacity when attached to the speakers necessary to meet audio requirements. Amplifiers shall be two channel amplifiers to allow paging to one circuit while playing alarm tone on another. B. FACP shall incorporate a spare automatic backup audio amplifier equal in size to the largest individual amplifier or be capable of backing up itself. |
A. Audio amplifiers shall be sized to provide ½ Watt minimum per attached audio speaker as shown on the drawings. Each audio amplifier shall have 50% minimum spare capacity when attached to the speakers necessary to meet audio requirements. B. FACP shall incorporate a spare automatic backup audio amplifier equal in size to the largest individual amplifier. |
| 2.6 MANUAL PULL STATIONS | A. Manual pull stations shall be addressable Simplex 4099-9001 single action or approved equal 1. Reset shall be accomplished with a lock and Simplex B key. |
A. Manual pull stations shall be addressable Simplex 4099-9001 single action or approved equal 1. Reset shall be accomplished with a lock and Corbin CAT #30 key. |
| 2.7 SMOKE DETECTORS/SENSORS -> A. Ceiling or area-type smoke detectors | 1. Detectors shall be photoelectric addressable analog with separate base. Part numbers 4098-9762 base and 4098-9714 head. | 1. Detectors shall be photoelectric addressable analog with separate base. |
| 2.7 SMOKE DETECTORS/SENSORS -> A. Ceiling or area-type smoke detectors | 4. When exposed back boxes are needed, use 4 square box painted red boxes of the appropriate size. | 4. When exposed back boxes are needed, use round ""wire mold"" boxes of the appropriate size. |
| 2.7 SMOKE DETECTORS/SENSORS -> B. Duct type smoke detectors | 7. In finished spaces mount remote indicator lights in close proximity to the duct smoke detector. Remote indicating lights shall be located on walls adjacent to detectors in corridor outside of room at a height between 48 and 96 inches. Indicating light location must be approved by UWMC Operations and Maintenance. | 7. In finished spaces mount remote indicator lights in close proximity to the duct smoke detector. Remote indicating lights shall be located on walls adjacent to detectors. |
| 2.8 HEAT DETECTORS | A. Heat detectors shall be combination of fixed temperature and rate-of-rise low profile addressable analog type and shall be "ordinary" temperature range in all areas except where located in a high ambient temperature area. Use Simplex Part 4098-9762 base and 4098-9733 detector. | A. Heat detectors shall be combination of fixed temperature and rate-of-rise low profile addressable analog type and shall be "ordinary" temperature range in all areas except where located in a high ambient temperature area. Use Simplex Part No. 0621151, PID 2098-9806 Remote Test Switch. |
| 2.10 AUDIBLE ALARM DEVICES | A. Speaker/strobes shall be white with red lettering, have sealed back, metal grill, with multiple wattage taps including ¼, ½, 1 watt, and 2 watts, and multiple candela taps including 15, 30, 75, or 110. Indoor speaker/strobes shall be Wheelock E70-24 MCW-FR or approved substitution. B. Install all speakers at the½-watt setting unless indicated otherwise on the drawings. Speakers located in rest rooms and similar enclosed areas where alarm threshold maybe high should be tapped at ¼ watt. Surgery Pavilion and Montlake Tower are 25V systems. Pacific and Cascade are 70V systems. C. Speakers shall be flush mounted or ceiling mounted. 1. Where necessary, surface mounting white Wheelock SBB box shall be used. |
A. Speaker/strobes shall be red, have sealed back, metal grill, with multiple wattage taps including ¼, ½, 1 watt, and 2 watts, and multiple candela taps including 15, 30, 75, or 110. Indoor speaker/strobes shall be Wheelock E70-24 MCW-FR or approved substitution. B. Install all speakers at the½-watt setting unless indicated otherwise on the drawings. Speakers located in rest rooms and similar enclosed areas where alarm threshold maybe high should be tapped at ¼ watt. C. Speakers shall be flush mounted. 1. Where necessary, surface mounting red Wheelock SBB box shall be used. |
| 2.11 STROBES (VISUAL ALARM) | A. Visual alarm signal shall operate at 24 volts DC and be equipped with a Xenon strobe flashing light which meets requirements outlined in 2.14 above. 1. Use Wheelock series STW or STWC. |
A. Visual alarm signal shall operate at 24 volts DC and be equipped with a Xenon strobe flashing light which meets requirements outlined in 2.14 above. 1. Use Wheelock series RSS-24MCW-FR. |
| 2.12 FLASHERS (PRIVATE MODE - VISUAL ALARM) | Removed | 2.12 FLASHERS (PRIVATE MODE - VISUAL ALARM) A. Flashing light with white lens and red ""FIRE"" lettering by Space Age. |
| 2.13 AUTO DOORS | 2.13 AUTO DOORS A. Doors equipped with operators are required to meet NFPA101 7.2.1.9. |
None |
| 2.15 FAN SHUTDOWN | 2.15 FAN SHUTDOWN A. Fire Alarm will have priority over building automation for fan shutdown commands to building HVAC. B. Building HVAC will restart automatically once the fire alarm system no longer calls for a shutdown. |
None |
| 2.17 SMOKE/FIRE DAMPERS | B. Interface relays shall be provided to operate 120VAC AC smoke dampers from the 24VDC fire alarm system. 5. Each fire/smoke damper shall be controlled with a single interposing relay. 6. The fire alarm system shall monitor the open, closed, and in between open and closed position of the fire/smoke dampers. Use 4090-9118 relay with T-sense. IAMs shall not be used due to idnet power consumption by the LED on the IAM. |
B. Interface relays shall be provided to operate 120VAC AC smoke dampers from the 24VDC fire alarm system. 5. Multiple fire/smoke dampers in common area per floor shall be controlled with a single interposing relay. 6. The fire alarm system shall monitor the open, closed, and in between open and closed position of the fire/smoke dampers. |
| 3.5 WIRING -> A. General wiring and raceway system. | 30. J-Boxes used for pull boxes shall not be installed within finished walls. | None |
| 3.5 WIRING | D. All initiating and signaling circuit devices shall be externally labeled with a printed adhesive label approximately ½” x 1” in size. Identify the node, circuit and zone, consistent with wire labeling scheme, using a 12 to 14 point font, black ink on white. Example: 14:M2-121 14:SIG15 14:SIG15/22 | D. All initiating and signaling circuit devices shall be externally labeled with a printed adhesive label approximately ½” x 1” in size. Identify the circuit and zone, consistent with wire labeling scheme, using a 12 to 14 point font, black ink on white. |
| 4.2 TESTING -> B. -> 3. -> c. | 15) All elevator, fan, door holder, damper and other control functions and circuits shall be tested for proper operation under alarm condition. | 15) All elevator, fan, door holder, damper and other control functions and circuits shall be tested for proper operation. |
October
General
General Information and Common Requirements
- General Information section –
- FDS Organization and Use subsection –
- Added paragraph “The FDS, Drawings and Specifications are complementary and what is called for by one shall be as binding as if called for by any others. Should the FDS, drawings, specifications and/or other instructions be contradictory in any manner, or should there be apparent errors in any, or should there be doubt as to the meaning of any, the Contractor shall refer the matter to the Owner whose decision thereon shall be conclusive and at no additional cost.”
- FDS Disclaimer subection –
- Edited first paragraph to read, “These standardsThe FDS areis not intended to replace codes, other design standards,manufacturer’s installation directions, the services of a professional design team, or professional architectural and engineering design analyses. Reference to codes, guides, or standard specifications of any Institute, Society or other organization or to any manufacturer’s installation directions, shall be the latest edition thereof, unless laws, ordinances, rules or regulations require compliance with a specific edition, in which case the reference shall be to such edition.”
- Edited second paragraph to read, “Consultants and/or contractors shall conduct their own independent evaluations and are liable for the final design. Any errors and omissions by the consultants and/or contractors for not following the FDS is at the responsibility of the associated party.”
- Added UW Medical Center Projects subsection
- FDS Organization and Use subsection –
Tunnels
- Utility Tunnels, Trenches, and Manholes –
- A. Design and Construction Requirements subsection –
- “General” subsection –
- Added item 5: “For all work within the tunnels and on associated utility systems and communication infrastructure, the abandonment of existing systems is not acceptable. Coordinate removal of disconnected mechanical and electrical utilities with Campus Utilities, communication infrastructure with UW IT, or fire alarm infrastructure with UW Fire Alarm Shop. Impacts to existing systems that must remain in service must be closely coordinated with the responsible UW entities listed above to ensure continuity of service. No variance requests will be granted.”
- Added item 6: “Do not construct facilities in such a way that negatively impacts the ventilation, access, or egress to the tunnel system. Existing manholes and personnel access points shall not be covered or impeded. Do not create any dead ends.”
- “General” subsection –
- A. Design and Construction Requirements subsection –
Environmental Health & Safety
-
Added new “Hazardous Materials Storage Cabinets” document
-
Added new “Laboratory Ventilation Design” document
August
General
General Information and Common Requirements
- General Information section -
- Sustainability subsection -
- Added 5th bullet point after first paragraph: “All appliances (clothes washers, dishwashers, ice makers, refrigerators, etc.) should be energy star rated.”
- Sustainability subsection -
- Requirements Common to All Disciplines section -
- Section C. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems
- Added 2nd to last paragraph in section: “When designing IoT and OT systems that will be connected to UW Facilities’ FACNET and BACNET networks, instance numbers for all devices shall be provided by the UWF Environmental Control Systems Manager (ECSM) (Shop 69, 206-685-8869 or 206-543-4208). The use of instance numbers that were not provided by the UWF ECSM is strictly prohibited. Prior to the activation of systems, the instance numbers shall be reviewed and approved in writing by the ECSM.”
- Section C. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems
Facilities Design Standards Variance Process
- Added new Facilities Design Standards Variance Process document as of August 2023
Preferred Manufacturer List
- Mechanical List -
- Manufacturer A column:
- In the Freeze Protection row, changed “Dowtherm HD” to “DOWFROST HD”.
- In the Water Treatment Controller row, removed “Nalco 3DTRASAR” and replaced with “Chem-Aqua aquaDART”
- Manufacturer A column:
Mechanical
- Section A. Design Criteria
- Design Criteria section –
- Added item 5: “Consider the impacts of wildfire smoke events. Review impacts to natural ventilation, operable windows, mechanical air filtration, etc.”
- Modified item 9, revised to: “Provide permanent guarded platforms as a means of accessing major equipment that needs to be maintained on a regular basis.”
- Modified item 10, revised to: “Provide access with platforms at each level for shafts that contain systems that require periodic maintenance, repair, or replacement (e.g. valves, dampers, and actuators), through access doors at a minimum size of 2’x4’.”
- Modified item 12, revised to: “Coordinate access method and platform requirements with Architect.”
- Design Criteria section –
- Section C. Air Handlers and Ventilation Fans
- Design Criteria section –
- Added item 9: “Where fume hood and general exhaust systems could be combined or separated, review design intent with EH&S and Engineering Services, including costs and benefits of the proposed solution.”
- Modified item 28: “A draw-through fan system is recommended. Typical arrangement of the components (in the direction of airflow) is heat recovery, heating water, and cooling coil.“
- Design Criteria section –
- Section D. Building Chilled Water Systems
- Installation, Fabrication and Construction section –
- Revised Central Cooling Water Building Header diagram
- Installation, Fabrication and Construction section –
- Section E. Building Steam and Condensate
- Design Criteria section –
- Removed content from item 1:
- “Heat all buildings with steam from the Power Plant whenever feasible.”
- “Do not use Steam radiant heating.”
- Modified item 2, revised to: “Convert Power Plant steam to hot water at all buildings to meet all heating requirements. If the building already has a low-pressure steam line, the steam can be used for steam-to-heating water or steam-to-hot water system.”
- Removed content from item 1:
- Installation, Fabrication, and Construction section –
- Modified item 4, revised to: “Provide strainers ahead of all traps.”
- Design Criteria section –
- Section F. Coils and Filters
- Coils section –
- Modified item 6 to include: “Where space design requires humidification, equipment should be located within the central system air handling unit. Provide adequate water treatment to prevent mineral buildup.”
- Products, Material and Equipment section –
- Modified item 1, revised to: “For legacy systems only, provide non-freeze type steam coils with perforated inner distribution tubes with vertical tubes; each section should be individually trapped. Tube wall thickness must be 0.035 inches (minimum).”
- Coils section –
- Section I. Ductwork and Duct Pressure Testing
- Smoke/Fire Dampers section –
- Modified item 1, revised to: “The smoke/fire dampers and their actuators are to be covered under the ductwork specialties section of the project specifications (not under controls or the fire alarm system). Exception: The position indication switch for smoke/fire damper pneumatic actuators is specified under the fire alarm system. Coordinate with electrical and refer to Environmental Health & Safety Design Guide – Fire Alarm System section.”
- Removed item: “Provide low voltage 24-volt actuators.”
- Modified item 7, revised to: “Provide damper blade position switch for position verification.”
- Smoke/Fire Dampers section –
- Section L. Potable and Nonpotable Water
- Design Criteria section –
- Added first paragraph: “All work shall be performed in accordance with applicable codes and standards as adopted by the authorities having jurisdiction including amendments.”
- Modified item 1, revised to the following:
- “When incoming water pressure exceeds 80 psig, provide a pressure reducing station with two parallel PRVs (each sized at 2/3 of total flow, each valved to operate independently). Where the minimum rated flow of the primary PRV’s is greater than 0, provide an additional low flow bypass PRV, sized to cover the range zero up to the minimum flow of the primary PRV.
- The assembly to include appropriate valves, strainers, gauges, drains, etc. and include a bypass.
- Where PRV’s are required, irrigation branch shall be taken off upstream of the main domestic water PRV, and the pressure shall be controlled independently of the domestic water system.
- Design the system to provide a minimum pressure at the highest point of the building as needed for connected systems or at 25 psig, whichever is greater.”
- “When incoming water pressure exceeds 80 psig, provide a pressure reducing station with two parallel PRVs (each sized at 2/3 of total flow, each valved to operate independently). Where the minimum rated flow of the primary PRV’s is greater than 0, provide an additional low flow bypass PRV, sized to cover the range zero up to the minimum flow of the primary PRV.
- Added item 2: “Provide a tee with a valved and capped connection for future growth in the domestic water header. The connection for future shall be sized to accommodate an additional 25% capacity beyond the current design capacity.”
- Modified item 3, revised to: “Provide the pressure backflow preventer devices in parallel, each sized at 2/3 of the total flow to prevent need for shutdown to test and repair.”
- Modified item 4, revised to: “Locate irrigation system backflow preventers inside the building mechanical room if possible. Otherwise, irrigation backflows are to be in non-public areas with adequate drainage and protection. Any irrigation connection will be provided upstream of the potable water system PRV assemblies and provided with a separate PRV where needed. Plumbing scope for irrigation systems will extend to the envelope of the building and will follow all standard plumbing specifications for valving, piping, etc.”
- Added item 6: “Protect the water system by installing laboratory faucets with built-in and un-removable vacuum breakers.”
- Removed item: “Control hot water recirculation based on based on HW recirculating return temperature. Monitor domestic and lab hot water supply and return temperatures in the DDC. Discuss alarming with Engineering Services.”
- Added item 10: “Heat pump water heater systems shall be piped through a swing tank to ensure that heated water does not route from the water heater directly to the building without a thermal buffer.”
- Modified item 15, revised to the following:
- “Unless otherwise specified by code, provide the following flow rates:
- Water Closets, Dual Flush = 1.28/ 1.1 gpf
- Urinals = 0.125 gpf
- Public Lavatories = 0.5 gpm
- Residential Lavatories = 1.2 gpm
- Showers = 1.5 gpm
- Kitchen Faucet = 1.8 gpm
- Metering faucets = 0.25 gpc”
- “Unless otherwise specified by code, provide the following flow rates:
- Removed item: “Piston type flush valve for urinal and water closet using reclaimed water is not acceptable.”
- Added item 23: “Use diaphragm type flush valves for urinal and water closets using reclaimed water supply.”
- Revised “Typical Building Water Header” diagram:
- Replaced single diagram with two different diagrams, one for non-lab buildings and one for lab buildings.
- Design Criteria section –
- Section N. Waste and Drains
- Design Criteria section –
- Added item 4: “When doing work in lab areas, please contact UW Facilities Engineering Services to ensure compliance with King County agreement dated 05-15-2022.”
- Design Criteria section –
- Section Q. Environmental Control Systems
- Interfacing the DDC with Equipment Build-In Controls section –
- Added item 1: “For air handling units and cooling towers, packaged controllers are strongly discouraged. UW preference is for direct control through BAS.”
- Removed item: “Indicate the relationship between the environmental control system and the dedicated (built-in) controls for specific HVAC equipment such as chillers, heat pumps, furnaces, and boilers.”
- Modified item 2, revised to: “When absolutely necessary, for equipment with packaged controllers, use built-in controls provided under other sections of the project specifications to handle staging and coordination of parts within each major piece of equipment. This provides a sole source of responsibility for the equipment’s performance to avoid damage to the equipment, to increase safety, and to increase Contractor and manufacturer responsiveness during problem solving.”
- Sensors section –
- Modified item 2, revised to: “Hard-wire critical sensors to local controllers. This includes but is not limited to steam converters, high-limit pressure switches, low-limit freeze stats, fire alarm and smoke control tie-ins and other sensors related to equipment failure or life safety.”
- Added new “Wildfire Smoke Event Provisions” section containing three items.
- Interfacing the DDC with Equipment Build-In Controls section –
- Section Y. Water Treatment and Flushing
- Installation, Fabrication and Construction section –
- “General” subsection –
- Added item 5: “Projects should hire the sole source contracted UW water treatment vendor (Chem-Aqua as of 2023); contact Engineering Services to verify water treatment vendor.”
- “General” subsection –
- Installation, Fabrication and Construction section –
- Preferred Manufacturer List
- Mechanical List –
- Manufacturer A column:
- In the Freeze Protection row, changed “Dowtherm HD” to “DOWFROST HD”.
- In the Water Treatment Controller row, removed “Nalco 3DTRASAR” and replaced with “Chem-Aqua aquaDART”
- Manufacturer A column:
- Mechanical List –
Electrical
Electrical Design Standards
- Section S. Panelboards
- Products, Materials and Equipment subsection –
- Modified item 3.d., revised to: “Provide minimum of 20% spare breakers for lighting panels and 25% spare breakers for receptacle and equipment branch panels which shall be available on the panelboards after construction is completed.”
- Products, Materials and Equipment subsection –
- Section AA. Lighting
- Basis of Design section –
- Design Criteria – Interior Lighting subsection –
- Modified item 3, added: “All interior fixtures are required to be LED fixtures.”
- Modified item 4, revised to: “Non-LED, custom, or special order fixtures require UW Engineering Services approval.”
- Design Criteria – Exterior Lighting subsection –
- Added item 2: “All exterior lighting are required to be LED lamp fixtures.”
- Modified item 3, revised to: “In general, pathway lighting in the UW Seattle campus are required to match the performance and appearance of the Archetype series AR/SAR by KIM lighting. Other types of light fixtures will need review and approval by the UW Landscape Committee and Engineering Services.”
- Modified items 6, revised to: “Repair or module replacement shall be accomplished quickly and without tools. The entire module is required to snap out without tools, and to include quick-disconnect plugs on all wiring. Allow for a new module to be quickly inserted to eliminate downtime.”
- Design Criteria – Interior Lighting subsection –
- Products, Materials and Equipment subsection –
- Modified item 4, revised to: “Defective parts replacement, including labor, tools, and access equipment by the manufacturer is required for 10 years after the certificate of occupancy date.”
- Modified item 5, revised to: “Provide 15% spare for each fixture type.”
- Basis of Design section –
- Section BB. Lighting Control
- Basis of Design subsection –
- Design Criteria subsection –
- Added item 2: “Control systems for new facilities and for major renovation projects shall be “wired” systems and shall be a 2-wire, “non-polarized” system.”
- Added item 3: “Wireless systems may be considered for renovation projects when the installation of conduit and wiring is not practical. Wireless systems needs approval from UW Facilities.”
- Added item 4: “Control systems that utilized batteries for devices and other equipment are not acceptable.”
- Design Criteria – Exterior Lighting Control subsection –
- Modified item 2, revised to: “All exterior lighting shall be controlled by NEMA rated contactors. Include an “Auto-On-Off-Manual” selector switch, that comply with Seattle Campus Lockout-Tagout procedures.”
- Design Criteria subsection –
- Basis of Design subsection –
- Added new section – II. Distributed Antenna Systems (DAS) – Puget Sound Emergency Radio Network (PSERN)
CAD & BIM standards
CAD and BIM design standards
- Section A. Standards, PDF Requirements, and Compliance Review Submittals
- CAD and BIM Compliance Submittal Review Requirements (format and content) section –
- Modified item 1 –
- Revised to: “BIM models shall utilize the latest Revit UW Resource Template”
- Added sub-item: “Email flrplans@uw.edu for the latest template”
- Modified item 1 –
- CAD Standards section –
- Modified item 3 –
- Added sub-item a: “All layers should be on and thawed
- Removed sub-item: “Use the latest Army Corps of Engineers A/E/C CAD standard found at https://erdc-library.erdc.dren.mil/jspui/bitstream/11681/33829/1/ERDC-ITL%20TR-19-7.pdf”
- Added sub-item b: “Layer name format shall follow AIA layer standards.”
- Modified item 6 – Added sub-items b through f:
- Item b: “Each room should be outlined with a polyline. It is used to calculate the area of the room.”
- Item c: “Room numbers should be located at the center of each room.”
- Item d: “Wall linework should be separated at partial height walls and glazing.”
- Item e: “Door swing should be drawn with Arc and not with polylines.”
- Item f: “Fixtures and casework shall be inserted as blocks and not individual lines.”
- Modified item 3 –
- BIM Standards section –
- Added item 1: “BIM models shall be submitted in Revit.rvt format.”
- Added item 2: “BIM models shall be submitted in Revit.rvt format.”
- Added item 3: “BIM models shall be submitted in Revit.rvt format.”
- Added item 4: “Packaging for Submission” and added the following sub-items –
- Item a: “Model should include shared coordinates”
- Item b: “Models must be detached from central.”
- Item c: “All worksets must be relinquished.”
- Item d: “On final export dialog box, UNCHECK the box saying “Export views on sheets and links as external references.” “
- Item e: “Use eTransmit to package model and related files.”
- CAD and BIM Compliance Submittal Review Requirements (format and content) section –
CAAMS
CAAMS Design Standards
- Section A. CAAMS – Campus Automated Access Management System
- Basis of Design subsection –
- Programming subsection –
- Modified first paragraph, revised to: CAAMS is used to control access at all exterior (zone) doors and at certain interior access control zones, such as computer labs, general purpose classrooms, office suites, audio/visual equipment rooms, and other zones with specific access concerns. To facilitate CAAMS, certain programming issues need consideration during design.”
- Programming subsection –
- Basis of Design subsection –
Exterior Improvements
Trees Standard Specifications
- Section A. Trees
- Added new subsection “Part 0 – Pre Construction and Site Planning” section.
- Part 3 – Execution subsection –
- 3.07 Removal of Tree/plant Protection: Damage or Loss Mitigation subsection –
- Modified item B, revised to: “Any trees or plants designated to remain, and which are damaged by the Contractor, shall be replaced in kind by the Contractor at their own expense and mitigated according to the tree mitigation formula. . Trees shall be replaced with a tree of similar species and of equal size or 6 inch caliper, whichever is less. Shrubs shall be replaced with a plant of similar species and equal size or the largest-size plants reasonably available, whichever is less. Where replacement plants are to be less than the size of the plant that is damaged, the Owner’s Representative shall approve the size and quality of the replacement plant.”
- 3.07 Removal of Tree/plant Protection: Damage or Loss Mitigation subsection –
Plants Standard Specifications
- Section A. Plants
- Part 1 – General subsection –
- 1.04 Quality Assurance subsection –
- Modified item C. sub-item 6, revised to: “Pruning: Pruning of woody plant material shall be performed according to ANSI A300 standards. For all trees, the Project Field Arborist will perform pruning to achieve aesthetic and functional goals.”
- 1.05 Delivery, Storage, & Handling subsection –
- Added item A: “Do not dump or store materials near structures, utilities, walkways, and pavements, or on existing turf areas or plants.“
- Added item B: “Provide erosion control measures to prevent erosion or displacement of bulk materials, discharge of soil-bearing water runoff, and airborne dust reaching adjacent properties, water conveyance systems, or walkways.”
- Modified item E. sub-item 4, revised to: “Do not prune prior to delivery unless otherwise approved by Architect. Allow Project Field Arborist one (1) week prior to tree delivery. Allow Field Arborist to perform any necessary structural pruning on trees prior to planting.”
- 1.04 Quality Assurance subsection –
- Part 1 – General subsection –
Environmental Health & Safety
Biohazard Laboratory Design
- Biohazards section –
- Added subsection 4: “Basic Laboratory Design for Bio-Safety Level 3”
- Subsection 5. Biological Safety Cabinets –
- Added item e. with sub-items: “Design Biological Safety Cabinets (BSC) to be installed as follows:
- Class II, Type A2 BSC shall be connected to the general exhaust system via a thimble connection unless approved by EH&S to recirculate into the room. The thimble will be provided by the BSC manufacturer and installed per manufacturer’s instructions and exhausted per Figure B at the end of this chapter.
- Class II Type B2 BSC shall be directly (hard) connected to a dedicated exhaust system.
- Class II Type B BSCs shall be interlocked with the exhaust fan so they shut down and alarm in the event of an exhaust fan/system failure.
- Class II Type B BSC exhaust shall be provided with a gas-tight valve that is accessible from the front or side of the cabinet; the purpose of this valve is to facilitate decontamination of the BSC.”
- Added item f: “Provide each Class II Type B BSC with a dedicated exhaust system unless an alternative design is demonstrated to provide the precise control necessary for cabinets to stay in tight tolerance limits.”
- Added item g: ” Provide each Class II Type B BSC with a bypass system for exhausting the room when the BCS fan is turned off; turning the BSC fan off saves filter life and the bypass facilitates decontamination of the BSC.”
- Added item h: “Thimble connection exhaust airflow shall be 120-125% of the BSC manufacturer’s exhaust specification.”
- Added “Bag In/Bag Out Unit” detail
- Added “Bio Safety Cabinet Duct Connection” detail
- Added item e. with sub-items: “Design Biological Safety Cabinets (BSC) to be installed as follows:
January
FDS Web page
- 2nd paragraph, statement now reads: "Any deviations to these standards shall be vetted through a documented resolution process AND APPROVED BY A REPRESENTATIVE FROM UWF SENIOR LEADERSHIP, prior to the completion of project design documents or maintenance contracts."
General information
- pg 2, section added: "Roof and Building Envelope Safe Access"
- pg 3, removed section "Coordination"
Requirements common to all disciplines
- Section B. Coordination:
- pg 1, Item #6 changed to Congested Spaces description
- new section added: "C. Internet of Things (IoT) / Operational Technology (OT) and Connected Digital Systems", pg 2
Civil
- Sec B. Surveying
- pg 4, item #7 "Potholing" added: "To minimize conflicts in the field, all existing utilities at the location of the proposed excavation shall be potholed prior to site disturbance."
Architectural
- section PARAPETS (B2010.50):
- pg 7, new item #1 added: "Parapets shall be 42” +/- 3” or higher."
Structural
- section A. General Requirements
- Design Live Load
- Structural Details
- Congested Spaces (removed and relocated to Requirements Common to All Disciplines)
- Penetrations
- Building Envelope Maintenance Equipment
- Vibration and Acoustics
- section B. Seismic Improvements and Building Modifications
- Seismic Upgrades
- URM Buildings
- Existing Structural Defects
- Seismic Upgrades
- section C. Foundations, Shoring, Slab on Grade, Sub-Grade Walls, Tunnels
- Foundations
- Montlake Landfill
- Foundations
- section E. Structural Materials
- Steel
- Timber
Mechanical
- Section A. Design Criteria
- Operational Constraints section –
- item 4 modified, revised to: “The installation of equipment in challenging-to-access spaces (such as atria, high ceiling areas, or confined spaces) must have a "maintenance access plan" included in the design documents and details. The plan must be reviewed and approved by the maintenance and repair staff at ES and UW shops. The plan should note at minimum the following: potential hazards, hazardous areas and a plan to mitigate safety risks in these areas, tasks to be performed in these areas, necessary equipment, and the responsible party for purchasing and storing equipment. A JHA template must be filled out before ordering equipment, with the Shop responsible for maintenance, and submitted with Closeout Documents. A link to access and download the JHA template can be found on this Job Hazard Analysis site. Additional JHA examples can be provided upon request.”
- Operational Constraints section –
- Section C. Air Handlers and Ventilation Fans
- Design Criteria section –
- Item 27 modified to add: “Design buildings to be positively pressurized relative to the outside.”
- Products, Materials and Equipment section –
- Changed “Fume Hood Fans” subsection title to, “Fume Hood Exhaust – Heat Recovery Air Handlers”
- Fume Hood Exhaust – Heat Recovery Air Handlers section – Added item 11: “In combined fume/general exhaust systems, provide means to safely replace filters and clean coils without exposing maintenance personnel or shutting down the fan system. Consider a bypass duct with low-leakage dampers around filters and heat recovery coils, or individual filters/coil on each redundant fan.”
- Fume Hood Exhaust – Heat Recovery Air Handlers section – Item 12 added: “Add a warning label on all access doors where filters or coils are installed within fume exhaust systems or combined fume/general exhaust systems. Warning label to state: “COMBINED LAB AND FUME HOOD EXHAUST AIR SYSTEM. DO NOT ENTER PLENUM WHILE AIRSTREAM IS ACTIVE.””
- Changed “Fume Hood Fans” subsection title to, “Fume Hood Exhaust – Heat Recovery Air Handlers”
- Products, Materials and Equipment section –
- Changed “Fume Exhaust Fans” subsection title to, “Individual Fume Exhaust Fans”
- Design Criteria section –
- Section D. Building Chilled Water Systems
- Programming section -
- item 5.a. modified, added: “Cross-connections that can introduce foreign water into the CCW system, such as 6-way valves, are not allowed.”
- Programming section -
- Section F. Coils and Filters
- Filters section –
- Added item 7: “Include pressure gauges on Merv 13 filters for air intakes above 500 cfm”
- Installation, Fabrication and Construction section –
- item 7 modified, added: ” Warning label to state: “COMBINED LAB AND FUME HOOD EXHAUST AIR SYSTEM. DO NOT ENTER PLENUM WHILE AIRSTREAM IS ACTIVE.””
- Filters section –
- Section I. Ductwork and Duct Pressure Testing
- Renovation and Expansion Projects section –
- added item 2: “When removing existing fume hoods, review with Engineering Services and EH&S and provide a complete mechanical design to determine how it will impact associated mechanical systems and to ensure that another means of general exhaust will be provided to the project area.”
- Smoke/Fire Dampers section –
- Item 10 modified, added: “Indicate unique device tag, manufacturer, model, dimensions, actuator type (electric or pneumatic), actuator brand, electrical panel, electrical circuit and actuator torque rating within damper schedule.”
- Installation, Fabrication and Construction section, in Duct Pressure Tests subsection –
- item 1 modified, revised to: “Pressure test 100% of all ductwork in shafts, all plenums, all fume exhaust ductwork, all snorkel exhaust ductwork and all hazardous exhaust ductwork. Additionally, all code required ductwork, two Owner selected supply ducts per floor, and one Owner selected exhaust or return duct per floor shall be tested.”
- Installation, Fabrication and Construction section, in Supply, Return, Non-Fume Exhaust, and Outside Air Ductwork Test Procedure subsection –
- items 1.d. and 2.f. removed
- Renovation and Expansion Projects section –
- Section V. Piping, Valves, Pressure Testing, and Accessories
- Installation, Fabrication and Construction section, in Pipe and Fittings subsection –
- Added item 4: “Where grooved mechanical joints are allowed, see standard specifications for requirements.”
- Installation, Fabrication and Construction section, in Pipe and Fittings subsection –
Electrical
- “Inspection, Calibration, and Testing – Standard Spec”, 1.02 Qualifications, E:
- “Western Electric Services” added to the list of “Pre-approved agencies, subject to the qualifications, third party requirements and associated restrictions stated in this section”
- “Short Circuit and Coordination Studies – Standard Spec”, 1.02 Qualifications, B:
- “Western Electric Services” added to the list of “Preapproved, subject to the Licensed PE requirements and the software analysis products specified in this section”
Conveyance
Conveyance Design Standards
- section A. Basis of Design
- pg 1, Design Criteria section
- new item #1 added:
- "1. Design of elevator systems shall be reviewed and approved by UW Elevator shop during the design phase of the project."
- new item #1 added:
- pg 2, Electrical section
- new item #6 added:
- "6. New Elevator Systems shall ONLY be connected to Emergency Power when required by Code or when requested and approved by the UW Elevator Shop. Existing emergency power connections to existing elevator systems may remain in place."
- item #7 (formerly #6) changed to:
- "7. Provide Battery Back-up for elevator systems in “high-traffic” areas or when deemed applicable by the UW Elevator Shop. All installations for battery back-up shall be vetted and approved by the UW Elevator Shop during the design phase."
- new item #6 added:
- pg 1, Design Criteria section
Conveyance Standard Specifications
- 2.06 POWER AND CONTROL DEVICES
- pg 17, item C. changed to
- "C. Emergency Power Operation: Connection to Emergency Power shall ONLY be provided when required by code or when requested and approved by elevator shop. When emergency power operation is required or approved for new controllers, provide the capability of emergency power operation as follows: Upon loss of normal building power, the elevators shall switch to emergency power operation."
- pg 18, new item D. added:
- "D. Battery Backup: Provide Battery Back-up for elevator systems in “high-traffic” areas or when deemed applicable by the UW Elevator Shop. All installations for battery back-up shall be vetted and approved by the UW Elevator Shop during the design phase."
- pg 17, item C. changed to
EH&S
Environmental Protection Requirements document changes made to the following sections:
- Sec 2. Stormwater Management
- Sec 7. Underground Storage Tanks
- Sec 8: Hazardous Waste Management
- Sec 9: Regulated Building Materials
Central Energy, Utilities & Operations
- A folder has been added to the downloadable Zip file containing all the documents that are available on the Campus Utilities and Operations Standard web page.
UW-IT
- A folder has been added to the downloadable Zip file containing all the documents that are available on the UW-IT Design Guide web page.
November
General
- All documents and tables named "Preferred Vendors and Products" have been renamed to "Preferred Manufacturer List".
Architectural
- Gender Neutral Restrooms, pg 2, section Multiple Occupant Restrooms
Added "Stall doors shall be installed with an occupancy indicator lock."
Mechanical
- Section A. Design Criteria
- pg 2, Design Criteria section
- Item #13 changed from: "Service elevator access is preferred for buildings with mechanical equipment on rooftops or in penthouses."
Changed to: "Service elevator access is required for buildings with mechanical equipment on rooftops or in penthouses."
- Item #13 changed from: "Service elevator access is preferred for buildings with mechanical equipment on rooftops or in penthouses."
- pg 2, Design Criteria section
- Section C. Air Handlers and Ventilation Fans
- pg 7, Design Criteria section
- Item #4 changed to: "Provide a permanent catwalk to access the upper portion of multi-level air handing units. Review with Engineering Services and the UW EH&S Safe Access team during the design phase of the project to ensure a clear understanding of the proposed solution."
- pg 7, Design Criteria section
- Section L. Potable and Nonpotable Water
- pg 37, Design Criteria section
- New item inserted at #13: "Hard wire electronic fixtures from facility power source."
- pg 37, Design Criteria section
- Section Q. Environmental Control Systems
- pg 46, Hardware and Software section
- Item #6 changed from: "Where compressed air is used for fire/smoke damper or DDC pneumatic controls"
Changed to: "Where compressed air is used for fire/smoke dampers or HVAC pneumatic controls"
- Item #6 changed from: "Where compressed air is used for fire/smoke damper or DDC pneumatic controls"
- pg 48, Renovation and Remodel Projects section
- New item inserted at #3: "New controls in existing buildings will match the existing approved manufacturers controls system in the building."
- pg 46, Hardware and Software section
- Preferred Manufacturer List, Mechanical
- item added: Product: Electric Motor Shaft Grounding Ring
- Manufacturer A: SGS-Shaft Grounding System CR Series
- Remarks: No Substitutions
- item added: Product: Electric Motor Shaft Grounding Ring
Environmental Health & Safety (EH&S)
- New files added under EH&S:
Office Ergonomic Furniture Design - Documents "Emergency Evacuation Sign Holders" and "Emergency Evacuation Floor Plan Inserts" were replaced with new versions to eliminate overlapping content.
July
Electrical
- Section W. Commissioning Support - Standard Specifications 3.01 A.3.a pg 86
"Spot network systems" inserted as item iii - New section added: HH. Photovoltaic Systems added
Mechanical
- Section D. Building Chilled Water Systems
- pg 12, Design Criteria section
- Item #9 removed: “Provide control sequence to automatically circulate water in hydronic coils at least weekly to remove sediment and replenish water treatment. This is especially important for fan coil units and chilled beams.”
- pg 12, Design Criteria section
- Section E. Building Steam and Condensate
- pg 16, Products, Material and Equipment section
- Item #2 removed: “Provide pneumatic rather than self-contained steam control valves on hot water converters.”
- pg 16, Products, Material and Equipment section
- Item #6 removed: “Provide 1” warmup bypass pipe with globe valve across all main building steam isolation valves and all tunnel steam isolation valves.”
- pg 16, Products, Material and Equipment section
- Section L. Potable and Nonpotable Water
- Item 13. "...refer to EH&S Laboratory Safety Guide." changed to "...refer to EH&S Emergency Washing Equipment Requirements" and new hyperlink installed.
- Section Q. Environmental Control Systems
- pg 46, Hardware and Software section
- Added item #5: “Provide pneumatic rather than self-contained steam control valves on hot water converters.”
- pg 46, Hardware and Software section
- Added item #6: “Where compressed air is used for fire/smoke damper or DDC pneumatic controls, provide redundant pressure reducing valves so they can be replaced or serviced without disrupting building operation.”
- pg 49, Added Metering & Monitoring section, with one item: “When a BTU meter is used for control, the temperature / flow values must be hard-wired outputs from the BTU panel to the DDC panel. Do not use network communication for control inputs.”
- pg 46, Hardware and Software section
Exterior Improvements - Plants
- Sec 1.04 - E. pg 5
- references containing "Architect" changed to "Architect and/or owner's representative"
- Sec 1.05 - C.4. pg 6
- content added:
"Alert UW Arborist 1 week prior to tree delivery. Allow UW Arborist to perform any necessary structural pruning on trees taller than 10 feet in height prior to planting."
- content added:
Exterior Improvements - Irrigation
- Products, Materials and Equipment 17.a.i. pg 6
- was:
"Use 4-inch risers in regular turf, 6-inch risers in eco-turf with approval, and 12-inch risers in beds." - changed to:
Use 6-inch risers in regular turf, and 12-inch risers in beds."
- was:
Environmental Health & Safety (EH&S)
- New files added under EH&S:
- Food Preparation Design Guide
- Safe Access and Maintainability
- Refrigeration Machinery Room Design & Construction
- Hazardous Materials Management
- Biohazard Laboratory Design
- Radioactive Materials - Non-Ionizing Radiation
- Radioactive Materials - Ionizing Radiation
- Evacuation Plan Sign Holders
- Evacuation Plan Inserts
- EH&s preferred vendors list
- New links added under EH&S for:
- UW Fall Protection Program Manual
- Fall Protection resources page
January
Architectural
- Section C. Interiors
- Interior Doors (C1030) -> Interior Doors Supplementary Components (C1030.90) -> Hardware (08 71 00), page 15:
- Item #8 added: "All exterior doors must have bottom latches and strikes. Surface mounted strikes with vertical rods are preferred. No concealed cable rods are permitted on University of Washington buildings."
- Interior Door Standard Specifications (08 71 00) -> 1.01 Products -> E. Exit devices, page 17:
- Item #5.a. removed: "Vertical Rods shall be cable type."
- Interior Doors (C1030) -> Interior Doors Supplementary Components (C1030.90) -> Hardware (08 71 00), page 15:
- Section D. Services
- Added Services section with content, page 22.
- Previous "Section D. Site Work" is now "Section E. Site Work".
Electrical
- New addition of Standard Specification section "Electrical Identification"
CAD & BIM
- The first three bullets in document "CAD and BIM standards" changed from:
- BIM models shall be submitted in Revit.rvt format in a mutually agreed upon release.
- All CAD files are to be submitted as an AutoCAD .dwg format.
- Remove all non-drawing files from drawing folder before submission, i.e.: .log, .bak, .svs, etc.
- changed to:
- BIM models shall be submitted in Revit.rvt format.
- Revit model files shall be named
<UW PDG Project Number>_<Discipline>_<Description>_v<Version>.rvt
CamelCase should be used for Descriptions longer than one word
i.e. (200001-A-ShellCore-v22.rvt). - Everything in the BIM model must be able to be exported to AutoCAD.
- Addition of new document "UW Architectural CAD Standard Layers (PDF)"
Space Guidelines
- Content added under "CLASSROOM/LEARNING SPACES", page 3:
- "1. In large classrooms (50 or more student seats), power (electrical outlet) shall be provided at all the ADA accessible seating areas."
Trees Standard Specifications
- Section 1.03 Contractor responsibility, page 4
- The numbered list under paragraph 3 changed from:
- a. $75.00/square inch for trees less than or equal to 6 inch diameter
- b. $50.00/square inch for trees greater than 6 inch and less than 18 inch diameter
- c. $40.00/square inch for trees greater than or equal to 18 inch diameter
- d. Cost is doubled for Trees of Distinction
- changed to:
- a. The assessed value of the tree using the Trunk Formula Method with a minimum value of $1000.00.
- b. Cost is doubled for Trees of Distinction (Exceptional, Historical, Memorial, Brockman Tour, Trees of Seattle)
- The numbered list under paragraph 3 changed from:
October
Environmental Health & Safety
Three documents were added under this section:
- EH&S - Emergency Washing Equipment.pdf
- EH&S - Environmental Protection Requirements.pdf
- EH&S - General Requirements.pdf
CAD & BIM Standards
Both documents in this section were revised:
- UW CAD and BIM Standards, Requirements, and Compliance.pdf
- CAD Check review checklist.pdf
Electrical
- BB. Lighting Control > Products, Material and Equipment
- Page 111: Manufacturer "nLight" was removed
Mechanical
The following sections have seen revisions:
- A. Design Criteria
- Design Criteria
- Interdiscipline Coordination
- Renovation and Demolition
- B. Central Plant Utilities - This was pulled from under A. Design Criteria and given its own section
- Power Plant Central Utilities > Steam and Steam Condensate
- Power Plant Central Utilities > Central Cooling Water (CCW)
- Power Plant Central Utilities > Compressed Air
- C. Air Handlers and Ventilation Fans
- Design Criteria
- Installation, Fabrication and Construction
- D. Building Chilled Water Systems
- Programming
- Design Criteria
- CCW-CPP Design Criteria
- CCW-WCUP Design Criteria
- CCW Header at Building
- Installation, Fabrication and Construction
- E. Building Steam and Condensate
- Design Criteria
- Installation, Fabrication, and Construction
- F. Coils and Filters
- Coils
- Filters
- Products, Material and Equipment
- Installation, Fabrication and Construction
- I. Ductwork and Duct Pressure Testing
- Dampers
- Smoke/Fire Dampers
- Products, Material and Equipment > Fume Exhaust Ductwork
- Products, Material and Equipment > Smoke/Fire Damper Actuators
- Installation, Fabrication and Construction > Supply, Return, Non-Fume Exhaust, and Outside Air Ductwork Test Procedure (renamed from "General Environmental Supply, Return, Exhaust, and Outside Air Ductwork Test Procedure")
- Installation, Fabrication and Construction > Fire Damper Tests
- J. Hydronic Heating
- Design Criteria
- Products, Material and Equipment
- Installation, Fabrication and Construction
- K. Compressed Air, Vacuum, Natural Gas & Nitrogen
- Design Criteria
- L. Potable and Nonpotable Water
- Design Criteria
- M. Central Pure Water – Reverse Osmosis / Deionized (RO/DI) (renamed from "RO/DI")
- Design Criteria
- Installation, Fabrication and Construction
- N. Waste and Drains
- Design Criteria
- O. Water Reclaim System
- Cistern
- Piping and Pumping
- Reclaimed Water Usage
- P. Commissioning
- Construction Submittals
- Q. Environmental Control Systems
- Approved Manufacturers and Installers
- Secure DDC Controls Room
- Hardware and Software
- Graphic Display
- Interface
- Interfacing the DDC with Equipment Built-In Controls
- Interfacing the DDC with Fire Alarm
- Sensors
- R. Identification
- Products, Material and Equipment > Piping
- Products, Material and Equipment > Plumbing Fixtures
- Products, Material and Equipment > Valves
- Products, Material and Equipment > Equipment
- Installation, Fabrication and Construction > Equipment
- S. Metering and Gauges
- Pipe Accessories
- T. Motors & VFDs
- Electric Motors
- Variable Frequency Drives
- U. Noise and Vibration Control
- Design Criteria
- V. Piping
- Design Criteria
- Products, Material and Equipment (Tables)
- Installation, Fabrication and Construction > Valves
- W. Pumps
- Installation, Fabrication and Construction
- Y. Water Treatment & Flushing
- Design Criteria
- Appendix - Preferred Vendors (Mechanical)
- Bypass Relief Valve - info removed
- Freeze Protection - changed from "Dowtherm HD" to "Dowfrost HD"
July
General
- "Coordination" page 3
- Paragraph added:
"To install anchor bolts or rebars into an existing reinforced concrete structure, contractor shall use scanner to locate the rebars in the existing structure, mark rebar locations on concrete and use core drill not jack hammer to make holes. Should the existing rebars be damaged, contractor shall repair the existing rebars at no cost to the University."
- Paragraph added:
Architectural
- Room Numbering standards (PDF) added to web page.
Mechanical
- Section A. Design Criteria and Campus and Power Plant Utilities
- "Operational Constraints" page 3
-
Paragraph 4 modified, now reads:
"Design documents and details for the installation of devices and/or equipment in spaces that are complicated to access for maintenance, (i.e. atria, high ceiling areas, confined spaces, etc), shall include a "maintenance access plan". ES staff and UW shops responsible for maintenance and repair operations in such spaces shall review and approve the plan."
-
- "Operational Constraints" page 3
Electrical
- Section A. General Requirements
- "Operational Constraints" page 2
- Paragraph 3 modified, now reads:
"Design documents and details for the installation of devices and/or equipment in spaces that are complicated to access for maintenance, (i.e. atria, high ceiling areas, confined spaces, etc), shall include a "maintenance access plan". ES staff and UW shops responsible for maintenance and repair operations in such spaces shall review and approve the plan."
- Paragraph 3 modified, now reads:
- "Operational Constraints" page 2
- Section G. Medium Voltage Switchgear
- "Design Evaluation" subsection removed.
- Section U. Switchboards
- "Design Evaluation" subsection removed.
April
Architectural
- Section C. Interiors
- "INTERIOR DOOR STANDARD SPECIFICATIONS (08 71 00)" content added, pages 16-20
Electrical
- Section A. General Requirements
- "Operational Constraints" page 2
- Paragraph 3 added:
"3. When designing the installation of devices in atria or high-ceiling areas, plans for the mechanical access of these devices must be submitted as part of the design documents."
- Paragraph 3 added:
- "Operational Constraints" page 2
Mechanical
- Section A. Design Criteria and Campus and Power Plant Central Utilities
- "Operational Constraints" page 3
- Paragraph 4 added:
"4. When designing the installation of devices in atria or high-ceiling areas, plans for the mechanical access of these devices must be submitted as part of the design documents."
- Paragraph 4 added:
- "Operational Constraints" page 3
February
Electrical
- The following sections were removed. These resources can be found on the Campus Utilities & Operations standard page.
- E. Electrical Meter and SCADA Integration and Commissioning – Standard Specs
- F. Electrical – Meter – Standard Specs
- G. Data Collection Controller – Standard Specs
Mechanical
- Section R. Metering and Gauges
- "Meter Installation" page 49
- Paragraph #1 changed to:
"1. Install and commission main meters and submeters as specified in UW Facilities Campus Utilities & Operations standards https://facilities.uw.edu/planning/utilities-standard." - Paragraph #3 changed to:
"3. Coordinate with UW Facilities CUO to involve them in all meter discussions during planning, design and construction. Campus Utilities & Operations to provide steam condensate meter wiring connection diagrams for each project. Contractor to provide wiring diagrams for other meters for review and approval." - Paragraph #4 removed.
- Paragraph #1 changed to:
- Page 51
- Mechanical Meter Profile Report removed.
- "Meter Installation" page 49
- Section U. Piping, Valves, Pressure Testing, and Accessories
- "Design Criteria" page 55
- Paragraph #6 and sub parts A and B removed.
- "Design Criteria" page 55
December
CAD & BIM
- Changed "CADCheck@uw.edu" to "flrplans@uw.edu".
Electrical
-
Table of Contents
-
The heading above sec A "Seattle Centralized Systems" changed to "Central Utilities Systems"; heading above sec K "Building Services" changed to "Building Secondary Distribution".
-
-
Section: Emergency Power Systems
-
Section R. Emergency Power Systems added; subsequent reodering of letters identifying Electrical sub-sections below section R.
-
-
Section: Electrical Meter and SCADA System
-
On page 10, the sentence reading "Coordinate with all the trades and disciplines involved. At minimum: fields installers of metering equipment, MV switches, transformers, transfer switches." changed to "Coordinate with all the trades and disciplines involved, including (at a minimum) field installers of metering equipment, MV switches, transformers, and transfer switches."
-
-
Section: Electrical - Meter - Standard Specs
-
On page 31, the sentence reading "Software shall operate on Windows 2000, XP, Windows 2003, VISTA, or Windows 7 operating systems." changed to "Software shall operate on the latest Microsoft operating system."
-
On page 34, the sentence reading "In the event the connections cannot be made as specified, the Contractor shall make the necessary corrections at his own expense." changed to "In the event the connections are not made as specified, the Contractor shall make the necessary CORRECTIONS at his own expense.
-
-
Section: Dry-type Medium-voltage Transformers - Standard Specs
-
On page 75 2.08-C, added "Ventilation openings shall be constructed to prevent any foreign object intrusion."
-
-
Section: Lighting Control
-
Products, Material and Equipment - Interior/Classroom Lighting Control Systems - "Approved manufacturers for centralized lighting control systems" changed to "Approved manufacturers for building network lighting control systems".
-
Products, Material and Equipment - Interior/Classroom Lighting Control Systems - Approved manufacturers for centralized lighting control systems: "Creston" removed, "nLight" added.
-
Duplicate heading for "Interior/Classroom Lighting Control Systems" corrected to 'Exterior Lighting Control Systems".
-
-
Section: Miscellaneous Signal Systems
-
Design Criteria 1.A: changed "Clock" to "Clock and centralized system interface".
-
Mechanical
- Section A: Design Criteria and Campus and Power Plant Central Utilities
Section I (previous version): Ventilation Design Criteria- Content under the headings Air Handlers, Fume Hood Fans, Fume Exhaust Fans, and Perchloric Acid Hoods were removed from under the heading for Compressed Air in Section A and placed into a new, separate section ("B"); section "I" Ventilation Design Criteria removed and its content added to new section "B"; subsequent reodering of letters identifying Mechanical sub-sections.
- Section D: Building Steam and Condensate
- Steam Trap Assembly drawing added to section D. Building Steam and Condensate.
UW Accessibility Guidelines
- Replaced version 1.0 (Dec 2019) with version 1.1 (Dec 2020).
October
A new section has been added called Architectural & Accessibility Guidelines (AAG) in the architectural section.
- It includes an Introduction, Scope of AAG and Disclaimer.
- Subsections follow the CSI section numbers: Concrete, Masonry, Metal, Wood Plastics & Composites, Thermal & Moisture Protection, Doors & Windows, and Finishes.
- New sections are Fall Protection, Hoists and Accessibility.
- Appendix A has links to other UW department sites that should be reviewed for UW campus requirements.
- References sections includes citations in the document
September
Major updates occurred in the following sections.
All Sections
- Updated department name to Engineering Services
- Updated dates to September 2017
Civil
- 02 G General Requirements – updated reference to Facilities Information Library
- 02 R Sanitary Sewers – updated reference to University Drawings 875RU-A through 875RU-E
- 02 U Utility Tunnels & Trenches – updated University drawing number references. Clarified that tunnel egress and ventilation should not be hindered by new projects. Increased minimum tunnel aisle width.
Mechanical
- 15 A General Requirements – Added references to new West Campus Utility Plant. Described exceptions to the FSDG. Updated code year reference.
- 15 B1 Potable and Nonpotable Water – Edited PRV minimum pressure. Adjusted potable and lab hot water heating system initial operating temperatures. Prohibited waterless urinals. Allowed dual-flush toilets.
- 15 B2 Waste and Drains – Recommends alternatives to backwater valve. Adds standpipe as high as practical as pressure relief valve terminations. Clarifies floors should be sloped to drain.
- 15 B4 Compressed Air, Vacuum, Natural Gas, Nitrogen – Added a liquid trap upstream of CA receiver. Clarified natural gas is available in some areas of campus. Edited requirement for contractor to ensure odor is present in natural gas immediately prior to turnover.
- 15 B5 RO/DI – Added check valve or p-trap with trap primer supplying suitable water quality on storage tank overflow pipe.
- 15 C1 Process and Environmental Chilled Water – omitted references required by current code. Adjusted minimum process chilled water loop system differential pressure. Modified expansion tank installation accessories. Added Nalco 3DTrasar water treatment controller for cooling towers.
- 15 C2 Central Cooling Water – Added description of new West Campus Utility Plant operation.
- 15 C3 Steam and Condensate – Revised to slip-type pipe expansion joints. Added 1” warmup bypass pipe at main building isolation valves and tunnel isolation valves. Added note to avoid steam traps that lose their prime during low-load conditions. Added note to avoid noise reduction orifice plates.
- 15 C4 Hydronic Heating – omitted references required by current code. Allowed heat pumps at remote off-campus sites. Switched to propylene glycol.
- 15 C5 Refrigeration – omitted references required by current code.
- 15 C6 Air Handlers and Ventilation Fans – added airflow measurement systems for fan arrays.
- 15 C8 Coils – switched to propylene glycol.
- 15 C9 Ductwork and Duct Accessories – added description for buried fiberglass reinforced plastic (FRP) ductwork/piping.
- 15 D Piping, Valves and Accessories – in pipe code P-1, allow stainless steel for above grade piping, and copper press fitting pipe joining on select systems. In pipe code P-4, note DeltaPValve by Flow Control Industries. In pipe code P-4, allow triple-offset and quadruple offset butterfly valves. In pipe code P-6, allow IR butt weld on generation skids. Provide generic wall sleeve seal system. Allow omission of balancing valves at VFD-driven pipes in some cases.
- 15 G Motors and VFDs – allow Class F or H motors. Omitted references required by current code. Allowed dual VFD or bypass starter for nonredundant critical applications. Added display and keypad for all drives.
- 15 H Metering and Gauges – Revised to new campus metering specification.
- 15 K Identification – updated background colors to reference plumbing code. Omitted references required by current code. Added service to equipment tag.
- 15 L Insulation – Allow cellular glass or polyisocyanurate insulation for CCW piping in tunnels. Add insulation on condensate water piping with waterside economizer.
- 15 M Water Treatment and Flushing – Added Nalco 3DTrasar for Water Treatment Controller.
- 15 R Environmental Control Systems – Fan preheat steam valves modified to fail closed.
- Addition of purchasing specifications
Electrical
- 16 M Metering and Monitoring – Revised to new campus metering specification.
- Addition of purchasing specifications